[ California energy website banner ]
DER Home
Background
DER Equipment
Research Initiatives
Installations
  • Atrium Hotel
  • Cupaiuolo Residence
  • Elihu Harris State Office Building
  • Franchise Tax Board
  • LADWP
  • Lopez Canyon Landfill
  • Pasadena City College
  • Raley's Superstore
  • Residential High Rise
  • Richmond-San Rafael Bridge
  • Santa Barbara County Jail
  • Santa Rita Jail
  • Sierra Nevada Brewing
  • UCLA Energy Services Facility
  • U.S. Postal Service
  • Yosemite National Park
    Economics
    Incentives / Funding
    Markets
    Interconnection
    Permitting
    Regulatory Activity & Policy
    Strategic Planning

    Notices / Announcements
    Reports
    DER Links

     Welcome to the California Distributed Energy Resources Guide
     Installations

    Residential High Rise, San Francisco, California

    Project Owners / Partners

    TECOGEN, Inc.
    1080 Chestnut Street Co-op

    DER Technology

    Natural gas, 60 kW IC engine packaged with heat recovery

    Overview

    The high-rise building at 1080 Chestnut Street in San Francisco added a 60 kW natural gas-fired cogeneration system in 1988. The system has produced over $40,000 in annual savings since its installation. Along with the 60 kW of electricity, the unit produces 440,000 Btu/hour of hot water. The system has also proven its reliability having been in operation since 1988.

    Contacts

    Doug McAbee, Property Manager for 1080 Chestnut Street
    TECOGEN, www.tecogen.com