Equipment Certification
Please note: this form is dated March 2002 and does not address newer Rule
21 testing requirements (IEEE 1547.1-2005 and UL 1741). Until a revised
version is prepared by the Rule 21 Work Group, this form may be modified by
the testing laboratory as needed to summarize the relevant results.
|
The following equipment has been tested by a Nationally Recognized Testing Laboratory as having met the Type Testing and Production Testing requirements of California Rule 21. Please note that the use of Certified Equipment is not a requirement for interconnection in California but intended to simplify the interconnection approval process.
DG equipment currently certified under Rule 21:
Capstone Turbine
- Model 330, 30 kW Microturbine Generator (Approved - 6/2005).
- Model 60, 60 kW Microturbine Generator (Approved - 6/2005)
- Model 65, 65 kW Microturbine Generator (Approved - 4/2007)
Fuel Cell Energy
- Model DFC300A-S, (Using a UL-Listed, SatCon Power Systems Canada, Ltd Model AE-462-60-F-A Inverter) (Approved - 2/2003)
- Model DFC300MA (Using Satcon Inverter Model AE-375-50-F-U-XX) (Approved - 7/2006)
- Model DFC300MA (Using ABB Inverter Model FCE SUB300) (Approved - 1/2007)
- Model DFC1500MA (Using Satcon Inverter Model AE-1500-60-F-U-XX) (Approved - 6/2006)
Plug Power
Tecogen
- Model CM60H, 60 kW Induction Generator (Approved - 3/2003)
- Model CM60L, 60 kW Induction Generator (Approved - 3/2003)
- Model CM75H, 75 kW Induction Generator (Approved - 3/2003)
- Model CM75L, 75 kW Induction Generator (Approved - 3/2003)
For detailed information on the tests conducted and the test results, please click on the document links below the listed piece of equipment.
Underwriters Laboratories - Distributed Generation Equipment and Energy Sources
UL is involved in the development of certification and performance testing requirements for grid interconnected devices. |
 |
 |
|
|