Public Participation
- Public Adviser's Office
- Power Plant Siting Proceedings FAQs
- Power Plant Siting or Licensing Process
- Six Phases of the Power Plant Siting Process
- Public Participation in the Siting Process: Practice and Procedure Guide (PDF File, 3.3 mb)
- Summary of Typical Public Involvement Opportunities in Energy Commission Siting Cases
- Public Adviser's Presentations and Printed Materials
- Commission Siting Division
- Title 20
Calif. Code of Regulations - Acronyms and Definitions Used in Siting Cases
- Energy Commission News Releases
To sign up for the Avenal e-mail ListServer, please enter the following information completely:
IMPORTANT NOTE: This page has been superceded by the Energy Commission's e-filing and e-commenting database and is no longer updated. To access documents for this proceeding, use the "Documents for this Proceeding (Docket Log)" and other e-filing links on this proceeding's home page.
Compliance Proceeding
Avenal Energy Power Plant
Docket Number:
08-AFC-1C -
(Compliance Proceeding)
Items are listed by the date of the meeting or event, where applicable.
- Order Approving a Petition to Modify Five and Add One Air Quality Condition of Certification. Posted February 6, 2013. (PDF file, 4 Page, 360 kb)
- Filing of Notice of Decision. Posted January 25, 2013. (PDF file, 1 Page, 33 kb)
- Notice of Receipt (Corrected) - Petition to Amend California Energy Commission Decision - The modifications proposed in the petition would allow Avenal Power Center,
LLC, to:
- extend the construction deadline for five years;
- allow the option to construct and operate the power plant as either a major stationary source of air emissions (as certified) or as a minor stationary source of air emissions; and
- make changes to four Air Quality Conditions of Certification relating to reissued Emission Reduction Credit certificate numbers and equipment descriptions.
- Notice of Receipt - Petition to Amend CEC Decision - Proposed Modification would allow the project to be constructed and operated as a minor source and make other administrative changes. (PDF File, 3 Pages, 57 kb)
Avenal Energy Project Response to Comments from the Center on Race, Poverty, & The Environment. Posted January 7, 2013. (PDF file, 12 pages, 492 kb)
California Energy Commission Response to Comment letter from Center on Race, Poverty, & The Environment Regarding the Amendment to the Avenal Energy Project. Posted January 4, 2013. (PDF file, 3 pages, 340 kb)
The Center on Race, Poverty & the Environment (CRPE) Comments Re: Avenal Energy Project Proposed Decision Modification (08-AFC-1C). Posted December 31, 2012. (PDF file, 36 pages, 705 kb)
California Energy Commission Staff's Analysis of Proposed Modifications to Allow for Construction and Operation As Either a Major or a Minor Stationary Source of Criteria Air Pollutant Emissions and to Make Minor Modifications to Air Quality Conditions of Certification. Posted November 20, 2012. (PDF file, 20 page, 258 kb)
Applicant's Request to Defer a Construction Deadline Extension Amendment. Posted November 1, 2012. (PDF file, 1 page, 80 kb)
Applicant's Petition For Post-Certification Amendment - to Extend the Construction Deadline, Allow Construction and Operation of the Avenal Energy Project as a Minor Source and Make Administrative Changes to Air Quality Conditions of Certification and Equipment Descriptions. Posted March 6, 2012. (PDF file, 29 pages, 120 kb)
Applicant's Petition For Post-Certification Amendment - to Allow Construction and Operation of the Avenal Energy Project as a Minor Source. Posted May 17, 2011. (PDF file, 287 pages, 5.8 MB) (Withdrawn 03/05/2012)