  APPLICATION FOR THE                 )	  
  COLUSA GENERATING STATION           )   DOCKET NO. 06-AFC-9
                                      )     
  ____________________________________)

COMMITTEE SCHEDULING ORDER



On December 13, 2006, the Application for Certification (AFC) was deemed data adequate for the twelve-month review process consistent with Public Resources Code section 25540.6. The Committee conducted a public informational hearing on January 25, 2007, to discuss the schedule and other issues of concern. The attached Committee Schedule is based on Staff's proposed schedule and related discussion at the informational hearing.

The Committee Schedule contains a list of events that must occur to complete the certification process in twelve months. It covers the period leading up to the Prehearing Conference and describes, without specific dates, the events that follow. The balance of the schedule will be determined at the Prehearing Conference.

Several milestones are dependent upon reviews to be conducted by federal, state, and local agencies as well as the timely provision of additional information by the Applicant. Key agency reviews are Colusa County's land use determinations and the Colusa County Air Pollution Control District's Determination of Compliance.

We may modify the schedule at any time upon either our own motion or that of a party. [Cal. Code Regs., tit. 20, § 1709(c)]. The schedule includes periodic status reports to determine whether case development is progressing satisfactorily, and to bring potential schedule delays or other relevant matters to our attention. If the parties and agencies are able finish their work earlier than this schedule projects, we stand ready to advance the hearing and decision dates accordingly.

Date Posted: February 1, 2007, at Sacramento, California. ENERGY RESOURCES CONSERVATION AND
DEVELOPMENT COMMISSION

________/signed/_______
JOHN L. GEESMAN,
Commissioner and Presiding Member
Colusa AFC Committee

________/signed/_______
JAMES D. BOYD,
Vice-Chairman and Associate Member
Colusa AFC Committee





COMMITTEE SCHEDULE
FOR THE
COLUSA GENERATING STATION PROJECT


DATE EVENT
December 13, 2006 AFC data adequate
January 25, 2007 Site Visit and Informational Hearing
February 12, 2007 Applicant files responses to Staff data requests
Mid-Late February, 2007 Staff conducts data response/issue resolution workshop
March 23, 2007 Local, State and Federal Agency draft
determinations, including air district's Preliminary
Determination of Compliance (PDOC) filed
March 30, 2007 Parties file Status Report #1
May 14, 2007 Staff files Preliminary Staff Assessment (PSA)
May 30, 2007 (If PSA not yet filed) Parties file Status Report #2
Early June, 2007 Staff conducts PSA workshop
June 11, 2007 Local, State and Federal Agency final
determinations, including air district's Final DOC filed
July 11, 2007 Staff files Final Staff Assessment (FSA)
July 18, 2007 (If FSA not yet filed) Parties file Status Report #3
Late July, 2007 Prehearing Conference
Tbd Evidentiary Hearings
Tbd Presiding Member's Proposed Decision (PMPD) issued for 30 day comment period
Tbd (near the end of PMPD comment period) PMPD comment hearing
Tbd Revised PMPD issued* for 15 day review period*
Tbd Energy Commission PMPD adoption hearing

Tbd = to be determined
* if necessary