COMMITTEE PROPOSED SCHEDULE |
||||||||||||||||
|
EL SEGUNDO POWER REDEVELOPMENT PROJECT
APPLICATION FOR CERTIFICATION DOCKET NO. 00-AFC-14 |
||||||||||||||||||
|
||||||||||||||||||
|
Dated: December 4, 2001 |
ENERGY RESOURCES CONSERVATION AND DEVELOPMENT COMMISSION |
|
ROBERT PERNELL |
WILLIAM J. KEESE |
|
|
|
|
|
|
|
Initial Critical Path Items Required from
Applicant -
|
|
|
|
Last Clarifying Data Requests
|
|
|
|
Data Responses Filed
|
|
|
|
Final Critical Path Items Required from Applicant -
|
|
|
|
Report adopted by Coastal Commission
|
|
|
|
Data Response/Visual Impact Workshops
(per Staff)
|
|
|
|
Staff files and serves "Supplement
to Staff Assessment"
|
|
|
|
Staff Workshops on Supplement to Staff
Assessment (per Staff)
|
|
|
|
Staff Files and Serves "Final Staff
Assessment" e
|
|
|
|
Committee Workshop(s)/Prehearing Conference
|
|
|
|
Committee Hearing Order
|
|
|
|
Testimony Filed and Served
|
|
|
|
Evidentiary Hearing (Possibly Preceded
by Committee Workshops)
|
|
|
|
Presiding Member's Proposed Decision (PMPD) Issued (Based on 'noticed" PDOC); Begin 30-day Public Comment Period |
|
|
|
End of Public Comment Period on PMPD
|
|
|
|
Commission Decision on PMPD (Next Scheduled
Business Meeting)
|
|
|
|
"Revised" PMPD Issued; Begin 15-day Public Comment PeriodEnd of Public Comment Period |
|
|
|
End of Public Comment Period on Revised PMPD |
|
|
|
Decision on Revised PMPD |
* Schedule is tolled until required item is provided.