IMPORTANT NOTE: This page has been superceded by the Energy Commission's e-filing and e-commenting database and is no longer updated. To access documents for this proceeding, use the "Documents for this Proceeding (Docket Log)" and other e-filing links on this proceeding's home page.



Gateway (Antioch) Power Plant Project
Compliance Proceeding

Docket Number: 00-AFC-1C

Compliance Notices

Compliance Documents

Petition for Conditional Approval of of Ownership Addition, Date Uploaded: February 3, 2006. (Adobe Acrobat PDF file, 44 pages, 180 kilobytes.)

Attachment A, Pictures and Drawings

Attachment C, Date Uploaded: February 3, 2006. (Adobe Acrobat PDF file, 4 pages, 40 kilobytes.)

Attachment D: New Water Treatment System Schematic, Date Uploaded: February 7, 2006. (Adobe Acrobat PDF file, 1 pages, 348 kilobytes.)

Attachment E: Enhanced Cooling Tower Blowdown Schematic, Date Uploaded: February 7, 2006. (Adobe Acrobat PDF file, 1 pages, 276 kilobytes.)

Attachment F: Oil Water Separator System Schematic, Date Uploaded: February 7, 2006. (Adobe Acrobat PDF file, 1 pages, 256 kilobytes.)

Attachment G: Water Mass Balance, Date Uploaded: February 7, 2006. (Adobe Acrobat PDF file, 1 pages, 540 kilobytes.)

CC8-New Water Treatment System , Date Uploaded: February 3, 2006.

CC8-Water Mass Balance.xls, Date Uploaded: February 3, 2006.

Letter from Mirant California LLC, dated July 6, 2004, regarding extension of construction milestones, Date Uploaded: July 28, 2004. (Adobe Acrobat PDF file, 2 pages, 108 kilobytes.)