Project Status: Amendment Approved; In Compliance Phase.
The California Energy Commission approved this project's Amendment on March 24, 2010. The Commission monitors the power plant's construction, operation and eventual decommissioning through a compliance proceeding.
Key Dates
- 10/1/2008 - GWF Energy LLC files Amendment Petition
- 10/14/2008 - Commission staff releases Staff Analysis.
- 3/24/2010 - Commission approved major amendment.
DESCRIPTION OF PROPOSED MODIFICATION
The modification proposed in the petition would involve converting the existing HEPP from a nominal 95-megawatt (MW) simple-cycle power plant into a combined-cycle power plant with a nominal 25 MW (net) of additional generating capacity. Though the plant would be renamed to the GWF Hanford Combined-Cycle Power Plant (GWF Hanford), it will retain the capability to operate in a simple-cycle configuration. New once-through steam generators (OTSGs) would be installed to allow the plant to be operated in its current simple-cycle configuration with no steam generation but with the selective catalytic reduction (SCR) and oxidation catalyst in operation, or to operate as a combined-cycle power plant generating an additional 25 MW (net) of power with new proposed emission limits.
For Questions About This Siting Case Contact:
For Questions About Participation In Siting Cases Contact:
Public Adviser
California Energy Commission
1516 Ninth Street, MS-12 Sacramento, CA 95814
Phone: 916-654-4489
Toll-Free in California: 1-800-822-6228
E-mail: PublicAdviser@energy.ca.gov
News Media Please Contact:
Media & Public Communications Office
Phone: 916-654-4989
E-mail: mediaoffice@energy.ca.gov
Proceeding Information
Calendar

Subscribe
Hanford Listserv
Automated E-Mail Notifications