HENRIETTA PEAKER PROJECT
APPLICATION FOR CERTIFICATION
DOCKET NO. 01-AFC-18
   
   
   
The California Energy Commission is the State agency granted exclusive authority to review and license proposals to construct and operate large electric power plants. GWF Energy LLC has filed a proposal to construct a peaker power plant project adjacent to the existing PG&E Henrietta Substation near the City of Lemoore in Kings County. A Committee of the Commission will begin the regulatory review process by conducting a Public Informational Hearing and Site Visit as described below:
Purpose of Hearing:: The Informational Hearing and Site Visit are the initial steps of the Commission's public power plant certification process, which contains requirements equivalent to those under the California Environmental Quality Act (CEQA) to review all relevant environmental and engineering aspects of the proposed project.

At the Informational Hearing, members of the general public, landowners, and representatives of other governmental agencies will have an opportunity to obtain information and offer comments on the proposal. The Applicant, GWF Energy, will explain its plans for developing the proposed site and related facilities. The Energy Commission staff will explain the regulatory review process and staff's role as independent experts in analyzing the project. The Applicant and the staff will also discuss possible issues that may be significant during the remainder of the proceeding.

Hearing Date & Place:

 

Wheelchair Accessible

Thursday, November 8, 2001
Beginning at 5:30 p.m.

City Council Chambers
City Hall, City of Lemoore
429 C Street ( at Fox Street)
Lemoore, California

Site Visit:
3:30 p.m.

Reservations Required:
(by November 6, 2001)

The Informational Hearing will be preceded by a Site Visit during daylight hours, at 3:30 p.m. Persons intending to attend the Site Visit should gather at the Lemoore City Hall parking lot. The Applicant will provide bus transportation.

Persons intending to attend the Site Visit should make a reservation for bus transportation with the Commission's Public Adviser at 916-654-4489 or toll free at 800-822-6228 or via e-mail pao@energy.state.ca.us not later than Tuesday, November 6, 2001.

Project Description:

GWF Energy LLC is seeking approval of a 4-month expedited Application for Certification from the California Energy Commission for the construction and operation of the Henrietta Peaker Project. The project is to the south of and contiguous to Pacific Gas and Electric Company's Henrietta Substation, which is approximately 20 miles southwest of Hanford, in unincorporated Kings County, California.

The project is a nominal 91.4-megawatt, simple-cycle power plant, on a seven-acre fenced site within a 20-acre parcel The project will consist of the power plant, an onsite 70-kilovolt (kV) switchyard, and approximately 550 feet of new 70-kV transmission line. Natural gas for the facility will be delivered via approximately 2.2 miles of new 12-inch pipeline that will connect to the existing Southern California Gas Company (SoCalGas) Line 800 transmission pipeline, approximately one mile south of the intersection of 25th Avenue and the Avenal Cutoff.

The project will use two General Electric LM6000 PC Sprint combustion turbine generators (CTGs), each with a base load nominal output of 46.9 MW at annual average conditions.

More Information:

www.energy.ca.gov/sitingcases/henrietta

In order to assist participants in understanding the project, the Commission Staff will prepare and file by November 5, 2001, an Issue Identification Report summarizing the potential major issues in the proceeding. Copies of this document may be obtained by calling the Commission's Project Manager at (916) 651-8835 or through the Commission's Web Site at www.energy.ca.gov/sitingcases/henrietta.

The environmental and engineering details of the proposed project are contained in the Application for Certification (AFC). Copies of the AFC are available locally at Kings County Library, 401 N. Douty Street., Hanford, California and Lemoore Branch Library, 457 C Street, Lemoore, California.

A draft Schedule for the proceeding is included in this Notice.

Help:

800-822-6228
(toll free in California)

916-654-4489

Members of the public may participate in all phases of the licensing process in a variety of ways. If you need information concerning public participation, please contact Roberta Mendonca, the Energy Commission's Public Adviser, at 916-654-4489 or, toll free in California, at 800-822-6228, or by e-mail at: pao@energy.state.ca.us

Information concerning the status of the project, notices and other relevant documents are available on the Commission's Web Site at: www.energy.ca.gov/sitingcases/henrietta

If you require special accommodation to participate in the Informational Hearing and/or Site Visit, please contact Priscilla Ross at least five (5) days before the hearing at 916-654-4489 or email at: pross@energy.state.ca.us

Contacts:

Technical questions concerning the project should be addressed to the Energy Commission Staff's Project Manager, Bob Eller, at 916-651-8835 or e-mail at: beller@energy.state.ca.us.

Questions of a legal or procedural nature should be directed to Garret Shean, the Hearing Officer, at 916-654-3893 or e-mail at: gshean@energy.state.ca.us

Media inquiries should be directed to Claudia Chandler, Assistant Executive Director for Media and Public Communications, at 916-654-4989 or by e-mail at: energia@energy.ca.gov



Dated: October 25, 2001

ENERGY RESOURCES CONSERVATION AND DEVELOPMENT COMMISSION


ARTHUR ROSENFELD
Commissioner and Presiding Member
Henrietta AFC Committee


MICHAL C. MOORE
Commissioner and Associate Member
Henrietta AFC Committee

 
 
 
 
HENRIETTA ACCELERATED 4-MONTH AFC SCHEDULE
DAY DATE ACTIVITY
  Oct-17 CEC determines Application is complete
  Oct-25 Notice of Informational Hearing, Site Visit & Schedule
Staff Files and Serves Data Requests
  Nov-8 Informational Hearing & Site Visit
Data Request Workshop(s) (per Staff)
  Nov-13 Committee Determines Application Qualifies: PRC 25552
Applicant Files Data Responses (per Staff)
  Nov-15








(Dec-6)
Initial Critical Path Items Required from Applicant -
  • Preliminary Determination of Compliance (PDOC)

  • Biological Opinion or Equivalent Demonstration of LORS Compliance

  • Cal-ISO Transmission Interconnection Review and Approval

  • "Will Serve" Letter or Equivalent from Water Supplier

  • Demonstration of NPDES Permit Compliance, if Necessary

  • Responses to All Data Requests Not Previously Submitted

  • Any Other Critical Path Item Known to Applicant

  Nov-21 Staff files and serves Staff Assessment
Staff Workshops on Staff Assessment (per Staff)
  Nov-29/30 Evidentiary Hearing (Possibly Preceded by Committee Workshops)
  Dec-28

(Feb-6)
Final Critical Path Items Required from Applicant -
  • Final Determination of Compliance (FDOC)

  • Adopted Final General Plan Amendment, Zoning Ordinance, and/or Conditions Required by Local Agencies but for CEC Jurisdiction


Possible Hearing on FDOC and Final Agency Comments
  Jan-9 End of Public Comment Period on PMPD
  Jan-9 Decision on PMPD
Or, if Necessary
    "Revised" PMPD Issued; Begin 15-day Public Comment Period
  149 End of Public Comment Period on Revised PMPD
  150 Decision on Revised PMPD
* IMPORTANT: At the Informational Hearing and Site Visit, Applicant shall identify the specific dates by which it shall provide the Initial and Final Critical Path Items. Applicant's failure to provide such items by the identified date will result in the continuance or suspension of the proceeding or a determination that the proceeding shall not continue under PRC 25552.