COMMITTEE ORDER ON ELIGIBILITY
|
|
HENRIETTA PEAKER PROJECT
APPICATION FOR CERTIFICATION, DOCKET NO. 01-AFC-18 |
||
Background On November 14, 2001, the full Energy Commission considered a Petition for Reconsideration of Resolution No. 01-1017-02 asserting that the Energy Commission does not have the authority to waive the requirements of Section 25552. The specific requirements in question are that the project not be a major source of air pollution and that the project convert to combined cycle or cogeneration within 3 years of initial operation. The matter was continued to December 5, 2001, for further consideration. In the absence of the waiver contained in Resolution No. 01-1017-02, the Henrietta project would not qualify for the expedited four-month process of Public Resources Code, section 25552. At the public Informational Hearing on November 8, 2001, the Applicant and local agencies presented information about the project as well as the largely completed local agency review of the project, including the unprecedented availability of the Final Determination of Compliance prior to the Informational Hearing. |
Discussion Given this current unsettled nature, and out of an abundance of caution related to legal requirements and processes, the Committee believes that this proceeding should go forward under the provisions of Public Resources Code section 25540.6. We base this decision on the state of readiness of the proceeding due to the Applicant's success in providing not only timely but early information, and our belief that the processing of this AFC should be accomplished as expeditiously as the readiness of the parties will allow. Thus, to provide immediate clarity and guidance to the Applicant, staff, governmental agencies, and the participating public, the Committee establishes the attached schedule. |
ORDER
|
|
Dated: November 15, 2001 |
ENERGY RESOURCES CONSERVATION AND DEVELOPMENT COMMISSION |
|
|
|
| DAY | DATE | ACTIVITY |
| 0 | Oct-17 | Energy Commission (CEC) determines Application is complete |
| Notice of Informational Hearing, Site Visit & Schedule | ||
| Staff Files and Serves Data Requests | ||
| Staff Publishes Issue Identification Report | ||
| Nov-8 | Informational Hearing & Site Visit | |
| Data Request Workshop(s) (per Staff) | ||
| Committee Determines Application Qualifies: Pub. Res. Code ¤ 25552 | ||
| Nov-14 | Applicant Files Data Responses (per Staff) | |
| 50 | Dec-7 | Initial Critical Path Items Required from Applicant -
|
| 60 | Dec-17 | Staff files and serves Staff Assessment |
| Dec-20 | Committee Workshop(s)/Prehearing Conference | |
| Dec-20 | Committee Files and Serves Hearing Order | |
| Dec-28 | Testimony Filed and Served | |
| Jan-4 | Evidentiary Hearing (Possibly Preceded by Committee Workshops) | |
| 89 | Jan-15 | Presiding Member's Proposed Decision (PMPD) Issued (Based on FDOC); Begin 30-day Public Comment Period |
| Feb-7 | Final Critical Path Items Required from Applicant -
|
|
| 119 | Feb-14 | End of Public Comment Period on PMPD |
| Feb-20 | Decision on PMPD (Regularly Scheduled Commission Business Meeting) |
| "Revised" PMPD Issued; Begin 15-day Public Comment Period | ||
| End of Public Comment Period on Revised PMPD | ||
| Decision on Revised PMPD |