DAY |
DATE |
ACTIVITY |
|
0 |
Oct-17 |
Energy Commission (CEC) determines Application is complete |
|
Notice of Informational Hearing, Site Visit & Schedule |
||
|
Staff Files and Serves Data Requests |
||
|
Staff Publishes Issue Identification Report |
||
|
Nov-8 |
Informational Hearing & Site Visit |
|
|
Data Request Workshop(s) (per Staff) |
||
|
Committee Determines Application Qualifies: Pub. Res. Code § 25552 |
||
|
Nov-14 |
Applicant Files Data Responses (per Staff) |
|
|
50 |
Dec-7* |
Initial Critical Path Items Required from Applicant -
|
|
60 |
Dec-17 |
Staff files and serves Staff Assessment |
|
Jan-4 |
Committee Workshop(s)/Prehearing Conference |
|
|
Jan-4 |
Committee Files and Serves Hearing Order |
|
|
Jan-14 |
Testimony Filed and Served |
|
|
Jan-17 |
Evidentiary Hearing (If Necessary & Possibly Preceded by Committee Workshops) |
|
|
Feb-1 |
Presiding Member's Proposed Decision (PMPD) Issued (Based on FDOC); Begin 30-day Public Comment Period |
|
|
Final Critical Path Items Required from Applicant -
|
||
|
Mar-6 |
End of Public Comment Period on PMPD |
|
|
Mar-6 |
Decision on PMPD (Regularly Scheduled Commission Business Meeting) |
Or, if Necessary
|
"Revised" PMPD Issued; Begin 15-day Public Comment Period |
||
|
End of Public Comment Period on Revised PMPD |
||
|
Decision on Revised PMPD |