In the Matter of:
Application for Certification
for the High Desert Power Project
____________________________
)
)
)
)
Docket No. 97-AFC-1

NOTICE OF PREHEARING CONFERENCE
and SCHEDULING ORDER



I. NOTICE OF PREHEARING CONFERENCE

NOTICE IS HEREBY GIVEN that the Committee will conduct a public Prehearing Conference as follows:

THURSDAY, FEBRUARY 18, 1999
Beginning at 10 a.m.
California Energy Commission
First Floor Hearing Room A
1516 Ninth Street
Sacramento, California
[Wheelchair Accessible]

At this event, all parties shall present their respective opinions concerning: which substantive topic areas are ready for evidentiary hearings; which require further analysis, including the nature of, and timeframe for, any such analysis; which topic areas the parties have reached agreement upon; and which remain subject to disagreement and require adjudication.

Interested agencies and members of the public are encouraged to attend and may comment at this Conference.

Purposes and Procedures

The basic purposes of the Prehearing Conference are to assess the parties' readiness for evidentiary hearings, to identify areas of agreement or dispute, and to discuss procedures which will assist the Committee in concluding this licensing process in as timely a manner as feasible. In this regard, the parties shall be prepared to discuss the matters mentioned above as well as future filing dates for testimony and other evidentiary documents, briefing and comment periods, and other related items.

Each party shall serve and file a Prehearing Conference Statement. These Statements must be received at the Commission Docket Unit, 1516 Ninth Street, MS-4, Sacramento, California 95814, no later than 5:00 p.m., on Tuesday, February 9, 1999. Identify these Statements with "Docket No. 97-AFC-1."

Each Statement shall specify:

Interested members of the public or governmental agencies may comment at the Prehearing Conference.

Anyone with a legitimate interest relevant to the siting of the proposed project may file a Petition to Intervene and become a formal party to the proceeding. Party status provides the rights to present independent evidence, receive pertinent documents, and cross-examine witnesses; it also imposes the duties to comply with various orders, procedures, and filing requirements, as well as be subject to cross-examination by other parties.

The Public Adviser's Office will assist anyone interested in preparing a Petition to Intervene. Commission regulations provide that a Petition to Intervene should be filed at least 30 days prior to the beginning of evidentiary hearings. [20 Cal. Code of Regs., sec. 1207(b)]. In this instance the Committee directs that any Petition to Intervene should be filed prior to the February 18, 1999, Prehearing Conference. Typically, by the time the Committee schedules a Prehearing Conference, intervenors are not granted time extensions to review existing case materials since to do so could delay the proceeding.

Those desiring information or assistance concerning participation in these proceedings should contact Roberta Mendonca, the Public Adviser, at (916) 654-4489 or, toll free, (800) 822-6228,or at mendonc@energy.state.ca.us. Rick Buell, the Staff Project Manager, will respond to technical inquiries and may be reached at (916) 653-1614. Questions of a legal or procedural nature should be addressed to Stanley W. Valkosky, the Hearing Officer, at (916) 654-3893. Please contact Robert Sifuentes at (916) 654-5005 if you require special accommodation to participate at this meeting.


II. SCHEDULING ORDER

The Committee last issued a Scheduling Order on October 6, 1998. Since that time, much additional data has been submitted. Based upon the October and November status reports, we expect further information to be submitted and events to occur according to the following schedule:

Air District releases revised Preliminary Determination of Compliance December 16, 1998
Applicant submits preliminary permit conditions from Lahontan Regional Water Quality Control Board January 13, 1999
Applicant files letters of intent and/or option contracts for emission reduction credits January 21, 1999
Staff Assessment issued January 21, 1999
Air District releases Final Determination of Compliance February 1, 1999
Parties file Prehearing Conference Statements February 9, 1999
Prehearing Conference February 18, 1999



Date placed online: December 22, 1998


ENERGY RESOURCES CONSERVATION
AND DEVELOPMENT COMMISSION




_____//signed//_____
JANANNE SHARPLESS
Commissioner
Presiding Member



_____//signed//_____
ROBERT A. LAURIE
Commissioner
Associate Member