Metcalf Power Plant Project - Main Page
[ California picture montage ]

PROJECT INFO

Project Fact Sheet

Project Location (Maps)

Project Photos

COMPLIANCE
PROCEEDING

Announcements, Documents,
Notices & Other Info
Relating to the
Compliance Proceeding

(Updated: 10/3/05)

Docket Log


ORIGINAL PROCEEDING

Notices, Orders,
Hearings & Workshops

(Updated: 9/18/01)

Documents,
Decisions and
Transcripts

(Updated: 11/02/01)

Docket Log


Schedule
For This Case


Proof of
Service List


List of
Reviewing Agencies

Commission
News Releases


PARTICIPATION

Public Adviser's Office

Guide to
Public Participation
In Siting Cases


Overview of
Siting Process


Title 20
Calif. Code of Regulations


Commission
Siting Division


Acronyms
Used in Siting Cases



 
METCALF
POWER PLANT PROJECT

Docket Numbers: 99-AFC-3C (Compliance Proceeding)
99-AFC-3 (Application For Certification)
99-SIT-3 (NOI Exemption, Request for Jurisdiction)


Committee Overseeing Original Application for Certification:

Robert A. Laurie, Commissioner
Presiding Member

  William J. Keese, Chairman, Commissioner
Associate Member

Hearing Officer: Stanley W. Valkosky
ANNOUNCEMENTS

To Be Announced

Also see our
Energy Calendar



Key Dates


Applicant's Information

  • Various documents from Calpine Corporation and Bechtel Enterprises Inc. and about the Metcalf Energy Center Power Project, including the Application for Certification, are available from here.


General Description of Project

The Metcalf Energy Center is a proposed a 600 megawatt (nominal) power plant located in southern San Jose, Calif., approximately one-half mile west of the Pacific Gas and Electric Company Metcalf substation. The plant will be constructed by Bechtel Enterprises Inc. and operated by Calpine Corporation. For more information, refer to the fact sheet for this project.

Links Regarding This Project

Applicant's Web Site:   www.metcalfenergycenter.com

Santa Teresa Community Web Site:   www.southsanjose.com

Santa Teresa Citizen Action Group:   www.santateresacitizen.org


Energy Commission Facility Certification Process

The Energy Commission is the lead agency under the California Environmental Quality Act (CEQA) and has a certified regulatory program under CEQA. Under its certified program, the Energy Commission is exempt from having to prepare an environmental impact report. Its certified program, however, does require environmental analysis of the project, including an analysis of alternatives and mitigation measures to minimize any significant adverse effect the project may have on the environment.


For Questions About This Siting Case Contact:
Steve Munro
Compliance Project Manager
Systems Assessment & Facility Siting Division
California Energy Commission
1516 Ninth Street, MS-15
Sacramento, CA 95814
Phone: 916-654-3936
E-mail: smunro@energy.state.ca.us

Internet E-Mail List Server will be available at:
smunro @ energy.ca.gov
(See List Server Page for subscription info.)



For Questions About Participation In Siting Cases Contact:

Public Adviser
California Energy Commission
1516 Ninth Street, MS-12 Sacramento, CA 95814
Phone: 916-654-4489
Toll-Free in California: 1-800-822-6228
E-mail: PAO@energy.state.ca.us



News Media Please Contact:

Claudia Chandler
Assistant Executive Director
Media & Public Communications Office
Phone: 916-654-4989
E-mail: mediaoffice@energy.state.ca.us




| Homepage | Commission Info | Licensing Main Page | Calendar | Site Index | Search Site | Links | Contact Us |

Page Updated: October 3, 2005