REVISION TO COMMITTEE SCHEDULING ORDER

On May 11, 2001 the Commission staff petitioned the Committee for a one-week delay in the publication date of the Preliminary Staff Assessment (PSA). The Committee Scheduling Order, issued on April 2, 2001 originally determined that the PSA would be issued on May 22, 2001. The need for the delay is supported by Staff's assertion that Applicant delayed in delivering data responses regarding several topic areas. The additional week will allow Staff to incorporate the recent data responses in the appropriate PSA sections.

The Committee hereby grants the Staff request and directs that the PSA be issued no later than May 29, 2001. No other elements of the case schedule are changed. Specifically, the Committee directs Staff to make all possible efforts to complete PSA workshops as per the April 2, 2001 Committee Scheduling Order.

Date On Line: May 11, 2001


ENERGY RESOURCES CONSERVATION
AND DEVELOPMENT COMMISSION




MICHAL C. MOORE
Commissioner and Presiding Member