[California Energy Commission Letterhead]


STATE OF CALIFORNIA

Energy Resources
Conservation and Development Commission




In the Matter of:                 )     Docket No. 00-AFC-12
                                  )     
Application for Certification     )
of Duke Energy for the            )     Application complete     	
Morro Bay Power Plant Project     )     January 10, 2001      
__________________________________)

 

 

COMMITTEE ORDER DIRECTING PARTIES
REPLY TO INTERVENOR'S PETITION

On May 23, 2001, Coastal Alliance for Plant Expansion (CAPE), an Intervenor in this proceeding, filed its Petition of Intervenor for Order Directing Duke Energy to Supply Information [1716(g)] (Petition). The Petition was timely filed pursuant to Title 20 California Code of Regulations, section 1716(g). It requests the Committee to issue an order directing Duke Energy North America (Applicant) to answer Data Requests 294 and 333. These are among the various data requests submitted by CAPE in its second set of requests. Applicant objected to five of the requests and CAPE takes issue with two of the five objections.

The Committee directs Applicant and Staff to respond to CAPEās petition no later than Friday, June 15, 2001. Such filings will be in lieu of any hearing to consider argument on the Petition. The Committee will issue its order ruling on the Petition no later than June 22, 2001.

 

Dated June 7, 2001 at Sacramento, California

 


MICHAL C. MOORE
Commissioner and Presiding Member
Morro Bay AFC Committee