STATE OF CALIFORNIA
Energy Resources
Conservation and Development Commission
In the Matter of: ) Docket No. 00-AFC-12 Application for Certification of ) Duke Energy for the ) Application Complete Morro Bay Power Plant Project ) January 10, 2001 _______________________________________)COMMITTEE RE: STATUS REPORTS
The Committee Revised Scheduling Order, issued October 2, 2001, did not specify dates on which the parties will file written Status Reports. Accordingly, the attached schedule specifies that parties are required to file Status Reports on Monday, October 22, and again on Monday, November 19, 2001. In addition, interested agencies such as the City of Morro Bay, the Central Coast Regional Water Quality Control Board, and the Coastal Commission are encouraged to file Status Reports addressing matters in this case which are of particular concern to each agency. Both parties and interested agencies should focus on matters which can affect the progress and schedule of the case, such as the preparation of studies, agreements, and testimony. In this way the Committee can learn of potential delays and/or concerns at a sooner, rather than later, time.
Also, please note the correction of a typographical error on the previously issued schedule regarding the date for the Prehearing Conference. The correct date is November 29, 2001.
So Ordered.
Dated October 11, 2001, at Sacramento, California.
MICHAL C. MOORE
Commissioner and Presiding Member
Morro Bay AFC Committee
WILLIAM J. KEESE
Chairman and Associate Member
Morro Bay AFC Committee
Schedule for the Morro Bay Power Plant
Revised October 11, 2001
DATE EVENT 9/7/01 SLOAPCD Files Final DOC 10/22/01 Parties File Status Reports 11/14/01 Staff Files Final Staff Assessment (FSA) 11/19/01 Parties File Status Reports 11/27/01 Parties File Prehearing Conference Statements1 11/29/01 Prehearing Conference 12/3/01
estimatedCCRWQCB files draft NPDES2 12/7/01 Parties File Testimony 12/17-19/01 Evidentiary Hearings 1/7-18/02 Evidentiary Hearings
1Prehearing Conference Statements to be served electronically on all parties.
2This date reflects a 19-day period between the FSA and the draft NPDES permit, as stated in the CCRWQCB letter dated September 17, 2001.
| Back to Main Page | Homepage | Calendar | Directory/Index | Search |