Moss Landing Power Plant Project
Documents

Docket Number: 99-AFC-4

Commission's Documents

Commission Decision & Order on the Moss Landing Power Project, October 25, 2000. Date Uploaded: November 8, 2000. Publication # 800-00-008 (Adobe Acrobat PDF file, 378 pages, 1.6 megabytes.)

Transcript of October 23, 2000, Committee Conference. Date Uploaded: November 2, 2000. (Adobe Acrobat PDF file, 47 pages, 91 kilobytes)

Committee Amendments to October 12, 2000, Errata and to the Presiding Member's Proposed Decision. Date Uploaded: October 26, 2000. (Adobe Acrobat PDF file, 4 pages, 29 kilobytes.)

Errata to the Presiding Member's Proposed Decision -and- Response to Comments. Date Uploaded: October 12, 2000. (Adobe Acrobat PDF file, 19 pages, 96 kilobytes.)

Transcript of September 21, 2000, hearing. Date Uploaded: October 4, 2000. (Adobe Acrobat PDF file, 198 pages, 241 kilobytes.)

Staff Follow Up on the Presiding Member's Proposed Decision for the Moss Landing Power Plant Project. Date Uploaded: September 15, 2000. (Adobe Acrobat PDF file, 2 pages, 15 kilobytes.)

Staff Comments on the Presiding Member's Proposed Decision for the Moss Landing Power Plant Project. Date Uploaded: September 15, 2000. (Adobe Acrobat PDF file, 10 pages, 37 kilobytes.)

Presiding Member's Proposed Decision for the Moss Landing Power Plant Project. Date Uploaded: August 29, 2000. (Adobe Acrobat PDF file, 373 pages, 1.4 megabytes.)

Staff's Responsive Brief Site Analysis for the Moss Landing Power Plant Project. Date Uploaded: August 2, 2000. (Adobe Acrobat PDF file, 11 pages, 24 kilobytes.)

Transcript of July 17, 2000, Committee Conference on the Moss Landing Power Plant Project. Date Uploaded: July 27, 2000. (Adobe Acrobat PDF file, 212 pages, 248 kilobytes.)

Transcript of June 20, 2000, Evidentiary Hearing on the Moss Landing Power Plant Project. Date Uploaded: June 29, 2000. (Adobe Acrobat PDF file, 218 pages, 251 kilobytes.)

BIOLOGICAL RESOURCES - ERRATA Commission staff testimony by Richard Anderson and Michael Foster. Date Uploaded: June 29, 2000. (Adobe Acrobat PDF file, 31 pages, 103 kilobytes.)

SOIL & WATER RESOURCES-ERRATA Commission Staff testimony by Joe O'Hagan, Dominique Brocard and Jim Henneforth. Date Uploaded: June 29, 2000. (Adobe Acrobat PDF file, 37 pages, 104 kilobytes.)

Transcript of June 15, 2000, Evidentiary Hearing on the Moss Landing Power Plant Project. Date Uploaded: June 26, 2000. (Adobe Acrobat PDF file, 89 pages, 128 kilobytes.)

Transcript of June 7, 2000, Evidentiary Hearing on the Moss Landing Power Plant Project. Date Uploaded: June 16, 2000. (Adobe Acrobat PDF file, 123 pages, 141 kilobytes.)

PART 3 of Final Staff Analysis of the Moss Landing Power Plant Project. Date Uploaded: June 9, 2000. (Adobe Acrobat PDF file, 98 pages, 242 kilobytes.)

LAND USE FIGURES FOR FINAL STAFF ASSESSMENT


PART 2 of Final Staff Analysis of the Moss Landing Power Plant Project. Date Uploaded: May 12, 2000. (Adobe Acrobat PDF file, 114 pages, 595 kilobytes.)

Transcript of May 8, 2000, Prehearing Conference on the Moss Landing Power Plant Project. Date Uploaded: May 18, 2000. (Adobe Acrobat PDF file, 86 kilobytes.)

PART 1 of Final Staff Analysis of the Moss Landing Power Plant Project. Date Uploaded: May 12, 2000. (Adobe Acrobat PDF file, 326 pages, 745 kilobytes.)

Status Report 7 on the Moss Landing Power Plant Project. Date Uploaded: April 24, 2000. (Adobe Acrobat PDF file, 1 page, 7 kilobytes.)

March 20, 2000. Status Report

Public Comment Form from Public Adviser Roberta Mendonca. Date Uploaded:: March 13, 2000.

Transcript of the February 24, 2000, conference on the Moss Landing Power Plant Project. Date Uploaded: March 3, 2000. (Adobe Acrobat PDF file, 29 pages, 34 kilobytes.)

Preliminary Staff Analysis of the Moss Landing Power Plant Project. Date Uploaded: February 11, 2000. (Adobe Acrobat PDF file, 457 pages, 5.4 megabytes.)

Staff Status Report #5, Date Uploaded: February 10, 2000. (Adobe Acrobat PDF file, 2 pages, 18 kilobytes.)

Staff Status Report #4, Date Uploaded: February 10, 2000. (Adobe Acrobat PDF file, 2 pages, 18 kilobytes.)

Local Map Showing Area Around the Moss Power Plant Project, Date Uploaded: January 28, 2000. (Adobe Acrobat PDF file, 1 pages, 270 kilobytes.)

Regional Map Showing Area Around the Moss Power Plant Project, Date Uploaded: January 28, 2000. (Adobe Acrobat PDF file, 1 pages, 402 kilobytes.)

Staff Status Report #3, Date Uploaded: December 10, 1999. (Adobe Acrobat PDF file, 2 pages, 18 kilobytes.)

Staff Status Report #2, Date Uploaded: November 8, 1999. (Adobe Acrobat PDF file, 2 pages, 18 kilobytes.)

Letter to Mark Seedall, Duke Energy, dated October 20, 1999, regarding staff data requests. (Adobe Acrobat PDF file, 2 pages, 32 kilobytes.)

Staff Status Report #1, October 7, 1999. (Adobe Acrobat PDF file, 2 pages, 20 kilobytes.)

Transcript of September 7, 1999 Informational Hearing and Site Visit (Adobe Acrobat PDF file, 82 pages, 163 kilobytes.)

Moss Landing Power Plant Project -- Issue Identification Report (Adobe Acrobat PDF file, 12 pages, 43 kilobytes.)

Moss Landing Power Plant Project -- Data Adequacy Recommendation (Adobe Acrobat PDF file, 69 pages, 364 kilobytes.)

Applicant's Documents

Moss Landing Power Plant Modernization Project 316(b) Resource Assessment, April 28, 2000. Prepared for: Duke Energy Moss Landing, LLC. (Adobe Acrobat PDF file, 343 pages, 7.2 megabytes.)

Evaluation of Proposed Discharge System with Respect to the Thermal Plan, Report by Duke Energy Moss Landing, LLC. Final Report, April 28, 2000. (Adobe Acrobat PDF file, 120 pages, 3.6 megabytes.)

Intervenor's and Other's Documents

No Other's documents at this time.

Figures and Maps