Condition of Certification BIO-7, found on pages 190-193 of the Presiding Member's Proposed Decision (PMPD), sets forth the criteria for implementing a $7 million plan to mitigate impacts of the proposed Moss Landing Power Plant Project (Project) due to entrainment of marine organisms. The Committee is interested in articulating in Condition BIO-7, specific performance criteria which will ensure that those who implement the detailed mitigation measures do so in a way which best compensates for the entrainment impacts of the Project. Therefore, the parties are directed to submit specific recommendations on the wording of Condition BIO-7 that may further achieve this goal.

In considering recommendations which may modify Condition BIO-7, the Parties should take into account the following factors:

Recommendations to modify Condition BIO-7 shall be submitted in strikeout-underline format and should reflect the factors above as well as guidance from the California Environmental Quality Act and relevant case law. Parties shall serve recommendations to all parties and to the Commission Docket Unit no later than the close of business on Thursday, October 5, 2000.

SO ORDERED.

Dated: September 27, 2000

ENERGY RESOURCES CONSERVATION
AND DEVELOPMENT COMMISSION




WILLIAM J. KEESE, Chairman
Presiding Member
Moss Landing AFC Committee




MICHAL C. MOORE, Ph.D., Commissioner
Associate Member
Moss Landing AFC Committee




| Back to Main Page | Homepage | Calendar | Directory/Index | Search |