SCHEDULING ORDER RE COMMITTEE

WORKSHOPS & EVIDENTIARY HEARING

MOUNTAINVIEW POWER COMPANY'S
MOUNTAINVIEW POWER PLANT PROJECT
Application For Certification Docket # 00-AFC-2












Purposes of Committee Workshops, Prehearing Conference & Evidentiary Hearings:

Based upon the anticipated filings by the Applicant (Siting Review Matrix and LORS Matrix) and the Staff (Verification Timetable) and Energy Commission Staff (Staff Assessment as well as the current status of regulatory review, the Committee believes it to be in the public interest to schedule the remainder of the proceedings as shown below.

As stated in previous orders, after the Applicant has completed, filed and served the Siting Review Matrix and the LORS Matrix, the Committee will conduct informal, public workshops as the forum to have the Staff, agencies, intervenors, and the public respond to the Applicant's analysis. If the Staff, agencies, intervenors or the public believe that the Applicant's assessment or proposed mitigation is insufficient, they may offer substantive additions or modifications to the Applicant's analysis or proposed mitigation or conditions so that consensus may be reached by alternative dispute resolution. Additionally, there may be suggestions to refine the Matrix itself.

For the Committee, the goal is to reach early consensus on matters not subject to contest on a complete description of a potential project impact and a satisfactory condition or alternative to mitigate the associated potential impact, all sufficient for inclusion in the Presiding Member's Proposed Decision.

Alternatively, any party to the proceeding may indicate at a pre-hearing conference concluding the workshops that it cannot reach consensus on a matter and may seek to adjudicate a material dispute of fact in a subsequent evidentiary hearing.

Using information from the workshops and evidentiary hearings, the Committee plans to ultimately use its version of the Siting Review Matrix and the LORS Matrix format in the Presiding Member's Proposed Decision to present the result of its deliberations on the project's environmental impacts and compliance with applicable laws. In addition, the Committee will use the Staff-produced Verification Timetable to present a foreshortened code identifying the timing and nature of verification submittals.

Critical Dates:

Staff Assessment File & Served Oct. 20, 2000
Committee Workshop Oct. 31 & Nov. 1, 2000 SacramentoAgric. Resources; Geology; Hazardous Materials; Water Quality;; Noise; Socioeconomics; Traffic/ Transportation; Public Health; Waste Management; Alternatives; Efficiency; Reliability; Facility Design; Transmission System Engineering; and Transmission Line Safety & Nuisance; and Worker Safety
Combined Committee Workshop & Prehearing Conference Nov. 6, 2000 San BernardinoAir Quality; Biology; Water Resources, Soils; Visual Resources; Cultural Resources; and Land Use
Evidentiary Hearings Nov. 16, 2000 SacramentoSiting Review Matrix, LORS Matrix, and Verification Timetable; Applicant's AFC and testimony; Staff Assessment; Preliminary Determination of Compliance; other evidence.
Issue Proposed Decision Early December 2000
Public Review & Comment Period 30 days after issuance of Proposed Decision
Commission January 20001

Comments on Schedule:

The Committee will not issue the final notices for the workshops and hearings until October 11, 2000. Any party may submit comments on the schedule proposed by this Order to the Hearing Officer, Garret Shean, at (916) 653-6421 or e-mail at: gshean@energy.state.ca.gov prior to October 11, 2000.

Important Notice:

The Committee is attempting to prepare the Proposed Decision in CD-ROM format as well as paper copy. The Committee, therefore, requests that all parties which have submitted or will be submitting materials on which they seek the Committee to rely in the preparation of the Proposed Decision make them available to the Committee in electronic form. Such electronic submittals should be made no later than the first evidentiary hearing.

Help:





(916) 654-4489

Members of the public may participate in all phases of the licensing process in a variety of ways. If you need information concerning public participation, please contact Roberta Mendonca, the Commission's Public Adviser, at (916) 654-4489, toll free in California at (800) 822-6228, or by e-mail at: pao@energy.state.ca.gov

Information concerning the status of the project, notices and other relevant documents are available on the Commission's Internet Web Site at:www.energy.ca.gov/sitingcases/mountainview

Technical questions concerning the project should be addressed to the Energy Commission Staff's Project Manager Kae Lewis, at (916) 654-4176 or e-mail at: klewis@energy.state.ca.gov

Questions of a legal or procedural nature should be directed to Garret Shean, the Hearing Officer, at (916) 653-6421 or e-mail at: gshean@energy.state.ca.gov

Media inquiries should be directed to Claudia Chandler, Assistant Executive Director for Media and Public Communications, at (916) 654-4989 or by e-mail at: energia@energy.ca.gov





Date On Line: September 28, 2000



ENERGY RESOURCES CONSERVATION
AND DEVELOPMENT COMMISSION




MICHAL C. MOORE, PH.D.
Commissioner and Presiding Member
Mountainview AFC Committee

ROBERT PERNELL
Commissioner and Associate Member
Mountainview AFC Committee