Order Granting Petition to Intervene
[California Energy Commission Letterhead]


STATE OF CALIFORNIA

Energy Resources
Conservation and Development Commission



In the Matter of:                   )      Docket No. 01-AFC-24
                                    )      DATA ADEQUATE
Application for Certification       )      FEBRUARY 6, 2002
PALOMAR ENERGY CENTER               )
BY SEMPRA ENERGY RESOURCES          )
____________________________________)
REVISED SCHEDULING ORDER

Background

Our initial Scheduling Order, dated March 29, 2002, anticipated that the City of Escondido would approve the Final EIR for the Escondido Research and Technology Center (ERTC) Specific Plan Amendment in September 2002. The City notified Staff by letter dated April 17, 2002, that the Specific Plan adoption date was changed to November 2002. Staff submitted a revised scheduling proposal that reflects the City's changed adoption date. (See, Staff's Status Report No. 5, dated August 23, 2002.) Applicant agrees with Staff's scheduling proposal except for the Biological Mitigation and Monitoring Plan submittal date. (See, Applicant's Status Report #5, dated August 26, 2002.)

The March 29, 2002, Scheduling Order stated that delays in the City of Escondido's ERTC Specific Plan Amendment process could affect the AFC schedule. The proposed ERTC Specific Plan Amendment includes land use modifications that are necessary for the proposed project to comply with local laws, ordinances, regulations, and standards (LORS). The parties understand that we will not commence evidentiary hearings until the City adopts the ERTC Specific Plan Amendment. As shown below, we have revised the AFC schedule to reflect the City's prospective adoption date.

Discussion

The following Revised Committee Schedule covers events that must occur before the Prehearing Conference. We will require the Applicant to submit all critical path items prior to publication of the Final Staff Assessment. The remainder of the Schedule will be determined at the Prehearing Conference. Since the City's review of the ERTC Specific Plan Amendment has been extended until November 2002, the parties have ample time to resolve pending issues that are identified in the PSA.

REVISED COMMITTEE SCHEDULE

DATE (2002) EVENT
August 28, 2002 Staff files Preliminary Staff Assessment (PSA)
Early September Applicant dockets Final Determination of Compliance (FDOC) from Air District
Mid-September Staff conducts PSA workshops
September 25 Parties file Status Reports # 6
Late Sept/Early Oct Committee Status Conference, if necessary
Mid-October Final EIR for the ERTC Specific Plan is available
October 23 Parties file Status Reports # 7
Mid-November City of Escondido certifies FEIR and acts on Specific Plan Amendment for the ERTC
November 20 Parties file Status Reports # 8
Mid-November Applicant submits all pending Critical Path items including the approved ERTC Specific Plan Amendment, FDOC, complete offset package, PM10 mitigation plan, data necessary to complete EJ analysis, resolution of transmission system mitigation issues, and Biological Mitigation and Monitoring Plan
Late November Committee Status Conference, if necessary
Late November Staff files Final Staff Assessment after Applicant provides all pending Critical Path items
To Be Announced Prehearing Conference

Dated August 29, 2002, at Sacramento, California.

_______________________________
JOHN L. GEESMAN
Commissioner and Presiding Member
Palomar AFC Committee

_______________________________
WILLIAM J. KEESE
Chairman and Associate Member
Palomar AFC Committee