In the Matter of: )  
  )        
  )     
APPLICATION FOR CERTIFICATION FOR THE
PASTORIA ENERGY FACILITY (PEF)
160 MW EXPANSION
BY CALPINE CORPORATION
)
)
)
)

     Docket No. 05-AFC-1
[Data Adequate 7/13/05]
      )           
   )        
_________________________________________ )       


ORDER DIRECTING PARTIES TO FILE STATUS REPORTS



The Presiding Member’s Proposed Decision (PMPD) was published June 8, 2006. The PMPD conference was held July 6, 2006. At the PMPD conference, Applicant Calpine Corporation (“Calpine”) requested a continuance of the certification process pending Calpine’s revision of its air quality offset package. Several months have passed without any update on the status of Calpine’s revision request. The Committee therefore directs the parties to file written status reports to explain the delay and to provide information on the anticipated schedule for concluding this matter.

Status reports shall be filed by 5 p.m. on Wednesday, October 25, 2006.





Dated October 18, 2006, at Sacramento, California.





________/signed/_______
JAMES D. BOYD
Commissioner and Committee Member
Pastoria Energy Facility Expansion AFC Committee