MODESTO IRRIGATION DISTRICT ELECTRIC
[California Energy Commission Letterhead]


BEFORE THE ENERGY RESOURCES CONSERVATION AND DEVELOPMENT COMMISSION
OF THE STATE OF CALIFORNIA



APPLICATION FOR A SMALL POWER PLANT )  
EXEMPTION FOR MODESTO IRRIGATION DISTRICT )  
ELECTRIC GENERATION STATION PROJECT (MEGS) ) DOCKET NO. 03-SPPE-01
SCHEDULING ORDER
__________________________________ )  

 

I. BACKGROUND

The Committee conducting this proceeding held an Informational Hearing and Site Visit on May 16, 2003. The parties discussed, among other things, scheduling matters at this event. Based upon these discussions, we establish the following schedule extending through publication of the Staff's Final Initial Study.

II. SCHEDULE


Date - Time

EVENT

May 30, 2003

Parties file Briefs re: Standard for
Initial Study/Negative Declaration

Period between June 5 to 13, 2003

Applicant files Data Responses

June 9, 2003

Parties file Status Reports

Period between June 12 to June 20, 2003

Data Response Workshop

June 30, 2003

Parties file Status Reports

Period between July 2 to July 14, 2003

Staff files Draft Initial Study

July 18, 2003

Parties file Status Reports

Period between July 24, 2003 to August 1, 2003

Staff files Final Initial Study

 

Dated May 21, 2003, at Sacramento, California.

 



JAMES D. BOYD
Commissioner and Presiding Member
MID SPPE Committee



ROBERT PERNELL
Commissioner and Associate Member
MID SPPE Committee