BEFORE THE ENERGY RESOURCES CONSERVATION AND DEVELOPMENT COMMISSION
|
| APPLICATION FOR A SMALL POWER PLANT | ) | |
| EXEMPTION FOR MODESTO IRRIGATION DISTRICT | ) | |
| ELECTRIC GENERATION STATION PROJECT (MEGS) | ) | DOCKET NO.
03-SPPE-01 SCHEDULING ORDER |
| __________________________________ | ) |
The Committee conducting this proceeding held an Informational Hearing and Site Visit on May 16, 2003. The parties discussed, among other things, scheduling matters at this event. Based upon these discussions, we establish the following schedule extending through publication of the Staff's Final Initial Study.
|
Date - Time |
EVENT |
|
May 30, 2003 |
Parties file Briefs re: Standard for |
|
Period between June 5 to 13, 2003 |
Applicant files Data Responses |
|
June 9, 2003 |
Parties file Status Reports |
|
Period between June 12 to June 20, 2003 |
Data Response Workshop |
|
June 30, 2003 |
Parties file Status Reports |
|
Period between July 2 to July 14, 2003 |
Staff files Draft Initial Study |
|
July 18, 2003 |
Parties file Status Reports |
|
Period between July 24, 2003 to August 1, 2003 |
Staff files Final Initial Study |
Dated May 21, 2003, at Sacramento, California.
|
|
|