APPLICATION FOR A SMALL POWER PLANT           )   DOCKET NO. 03-SPPE-01
EXEMPTION BY MODESTO IRRIGATION DISTRICT      )         ORDER re
FOR THE MODESTO ELECTRIC GENERATION           )       REPLY BRIEFS
STATION PROJECT (MEGS)                        )
______________________________________________)





The parties submitted Opening Briefs for this case on October 1, 2003. After considering the matters discussed in those briefs, the Committee has elected to provide the parties an opportunity to submit Reply Briefs.

Parties submitting a Reply Brief must docket and serve such a Brief no later than 3:00 p.m., on Friday, October 17, 2003.



Date online: October 9, 2003 at Sacramento, California.



JAMES D. BOYD
Commissioner and Presiding
Member MEGS SPPE Committee



ROBERT PERNELL
Commissioner and Associate
Member MEGS SPPE Committee