BEFORE THE ENERGY RESOURCES CONSERVATION AND DEVELOPMENT COMMISSION
OF THE STATE OF CALIFORNIA
APPLICATION FOR CERTIFICATION ) DOCKET NO. 04-SPPE-01
FOR A SMALL POWER PLANT EXEMPTION )
RIVERSIDE ENERGY RESOURCE CENTER ) SCHEDULING ORDER
_______________________________________)
I. BACKGROUND
The Committee conducting this proceeding held an Informational Hearing and Site Visit on May 26, 2004. The parties discussed, among other things, scheduling matters at this event. Based upon these discussions, we establish the following schedule extending through publication of the StaffÕs Final Initial Study.
II. SCHEDULE
| DATE |
EVENT |
| June 14, 2004 |
Applicant files Responses to Staff Data Requests |
| June 18, 2004 |
Data Response and Issue Resolution Workshop |
| July 7, 2004 |
Last day to file Petition to Intervene |
| July 9, 2004 |
Staff files Draft Initial Study |
| July 16, 2004 |
Agencies Comment on Draft Initial Study |
| July 16, 2004 |
Draft Initial Study Workshop |
| July 29, 2004 |
Staff files Final Initial Study |
Dated May 28, 2004, at Sacramento, California.
|

JACKALYNE PFANNENSTIEL
Commissioner and Presiding Member
RERC SPPE Committee |

JOHN L. GEESMAN
Commissioner and Associate Member
RERC SPPE Committee
|
|