Central Valley Committee Scheduling Order
[California Energy Commission Letterhead]


STATE OF CALIFORNIA

Energy Resources
Conservation and Development Commission



APPLICATION FOR CERTIFICATION OF THE ) DOCKET NO. 01-AFC-22
CENTRAL VALLEY ENERGY CENTER ) APPLICATION COMPLETE
IN FRESNO COUNTY ) (DATA ADEQUATE)
(CENTRAL VALLEY ENERGY CENTER, LLC) ) JANUARY 9, 2002
___________________________________________ )  


COMMITTEE SCHEDULING ORDER

This Scheduling Order is based on discussions at the February 7, 2002, Informational Hearing and the schedules proposed by the Energy Commission staff (Staff) in its January 28, 2002, Issue Identification Report. Applicant concurs in the schedule proposed by Staff.

The attached Committee Schedule contains a list of events that must occur in order to complete the certification review in a timely manner. Several deadlines listed in the schedule are contingent upon reviews and analyses to be conducted by other federal state and local agencies. If those reviews are not completed on or before the dates listed in the Committee schedule, the Committee may need to modify the schedule.

The attached Committee schedule only covers the period through release of the Staff Assessment Addendum. The balance of the schedule will be determined following issuance of the Staff Assessment Addendum and will be based upon the progress of the parties and the status of the reviews and analyses conducted by other agencies.

The Commission staff is responsible for meeting all Committee deadlines for the filings produced by the staff. The Applicant bears the burden of proof in this proceeding and must be responsible for the timeliness of its own filings as well as those of all other agencies outside the Commission. Thus, a delay by an agency other than the Commission staff in filing a required document may result in a necessary extension of the Committee schedule. In addition, the Committee may modify the schedule at any time either upon its own motion or that of a party. (Cal. Code of Regs., tit. 20, § 1709, subd. (c).)

For information on public participation, please contact the Commission's Public Adviser, Roberta Mendonca at (916) 654-4489 or toll free at (800) 822-6228 or by e-mail at: pao@energy.state.ca.us .

Technical questions concerning the project should be addressed to the Commission's Project Manager Mathew Trask, at (916) 654-4067 or e-mail at: mtrask@energy.state.ca.us .

Questions of a legal or procedural nature should be directed to Cheryl Tompkin, the Hearing Officer, at (916) 654-3893 or e-mail at: ctompkin@energy.state.ca.us .

If you require special accommodation to participate in this event, please contact Priscilla Ross at (916) 653-6631 or e-mail at: pross@energy.state.ca.us .

Media inquiries should be directed to Claudia Chandler, Assistant Executive Director for Media and Public Communications, at (916) 654-4989 or e-mail at: energia@energy.ca.gov .

Information concerning the status of the project, as well as notices and other relevant documents, is also available on the Energy Commission's Internet home page at: http://www.energy.ca.gov/sitingcases/cvec/index.html .



Dated: February 21, 2002, at Sacramento, California.


ARTHUR H ROSENFELD
Commissioner and Presiding Member
Central Valley Energy Center Committee


ROBERT A. LAURIE
Commissioner and Associate Member
Central Valley Energy Center Committee





COMMITTEE SCHEDULE FOR CENTRAL VALLEY ENERGY CENTER


DAY

DATE

ACTIVITY

0

Jan. 9

Energy Commission (CEC) Determines Application Is Complete

15

Jan. 24

Staff Files and Serves First Set of Data Requests

19

Jan. 28

Staff Files Issue Identification Report

29

Feb. 7

Informational Hearing and Site Visit

42

Feb. 21

Committee Files and Serves Scheduling Order

47

Feb. 25

Data Responses Due From Applicant

57

Mar. 7

Data Response and Issue Workshop

61

Mar. 11

Local, State and Federal Agencies File Preliminary Determinations of Compliance

75

Mar. 25

USFWS Files Draft Biological Opinion or Statement that Informal Consultation is Appropriate

75

Mar. 25

Staff Files and Serves Preliminary Staff Assessment (PSA)

90

April 9

Staff Holds PSA Workshop(s)

100

April 19

Local, State and Federal Agencies File Final Determination of Compliance (FDOC)

110

April 29

Staff Files and Serves Staff Assessment Addendum