In the Matter of: ) Docket No. 01-AFC-19 ) Application for Certification for the ) (AFC Accepted 11/14/01) ) SMUD COSUMNES POWER PLANT ) _______________________________________)
ORDER GRANTING PETITION TO INTERVENE
Upon consideration of the Petition to Intervene filed by the California Unions For Reliable Energy (CURE), the Committee designated to conduct proceedings in this matter makes the following findings:
- On January 29, 2002, a Petition to Intervene in the above-captioned proceeding was filed by:
CURE
C/O Marc D. Joseph, Esq.
Mark R. Wolfe, Esq.
Adams Broadwell Joseph & Cardozo
651 Gateway Blvd., Suite 900
South San Francisco, California 94080
- The Petition was timely filed and contains the information required by section 1207 of the Commission's regulations (Cal. Code of Regs., tit. 20, § 1207);
- The Applicant has filed no opposition to said Petition; and
- Petitioner's interests are relevant to the above-captioned proceeding.
THEREFORE, the Committee Orders that the Petition to Intervene in this matter be GRANTED and that Petitioner be placed upon the Proof of Service List as an Intervenor; Staff shall ensure that Petitioner immediately is provided with a copy of the Application for Certification document. Petitioner may exercise the rights and shall fulfill the obligations of a party as set forth in Title 20 of the Californian Code of Regulations.
Dated March 15, 2002, at Sacramento, California
ROBERT PERNELL
Commissioner
Presiding Member
ARTHUR H. ROSENFELD
Commissioner
Associate Member