The purposes of the Project Status Hearing are to review:
1.   the status of the proceeding,
2.   the timeliness and completeness of Applicant data submissions, and
3.   the schedule for the remainder of the Application for Certification (AFC) proceeding.

 

 
 
Discussion:

Following a May 14, 2002, Hearing on Project Status, and an Energy Commission Staff workshop, the Committee received a jointly proposed schedule from Staff and Applicant. On June 5, 2002, the Committee promulgated the "Committee Schedule" which enumerated a number of critical path items necessary for the preparation and public release of the Preliminary Staff Assessment and the Final Staff Assessment. On August 8, 2002, the Staff issued its Preliminary Staff Assessment (PSA) with certain topics not addressed.

Both the Staff and SMUD have filed monthly Status Reports since the publication of the Committee Schedule. Staff has reported that as of December 2002 one critical path item, a Biological Assessment accepted by USFWS and NMFS, has not been accomplished by SMUD; and therefore, the Final Staff Assessment cannot be completed. In the schedule jointly proposed by SMUD, it asserted that the Biological Assessment would be accepted by USFWS and NMFS in July or August 2002. The acceptance of SMUD's Biological Assessment leading, if adequate, to the completion of a federal Biological Opinion and the issuance of a federal permit are prerequisites for SMUD to begin construction of its project.

To assist the Committee in this matter, Staff, Applicant, and the other parties shall be prepared to present scheduling suggestions and discuss scheduling options at the hearing noticed below.

 
 
 
Hearing Date &
Place:


Wheel chair accessible

To consider the appropriate action, the Committee will conduct a hearing as follows:

Monday, January 13, 2003
Beginning at 1:30 p.m.

California Energy Commission
Hearing Room A
1516 Ninth Street
Sacramento, California



Teleconference:


As a convenience, parties and members of the public who cannot attend the hearing in person may participate by calling the toll-free number for the proceeding: 1-888-655-9181. (Passcode; "SMUD." Leader: "Garret Shean.")

 
 
Status Reports:On or before January 10, 2003, the Commission staff and the Applicant shall file and serve a Status Report regarding the timeliness and completeness of the Applicant's submissions to the federal agencies, any known schedule for federal review and permitting.

 
 
Assistance:

800-822-6228
(toll free in California)

916-654-4489

Members of the public may participate in all phases of the licensing process in a variety of ways. If you need information concerning public participation, please contact Roberta Mendonca, the Energy Commission's Public Adviser, at 916-654-4489 or, toll free in California, at 800-822-6228, or by e-mail at: [pao@energy.state.ca.us] Persons requiring special assistance contact Lou Quiroz, (916) 654-5146, five days prior to the hearing.

Information concerning the status of the project, notices and other relevant documents are available on the Commission's Web Site at: documents are available on the Commission's Web Site at:

www.energy.ca.gov/sitingcases/smud/

 
 
Contacts:Technical questions concerning the project should be addressed to the Energy Commission Staff's Project Manager, Kristy Chew, at 916-654-3929 or e-mail at: [kchew@energy.state.ca.us]

Questions of a legal or procedural nature should be directed to Garret Shean, the Hearing Officer, at 916-654-3893 or e-mail at: [gshean@energy.state.ca.us]

Media inquiries should be directed to Claudia Chandler, Assistant Executive Director for Media and Public Communications, at 916-654-4989 or by e-mail at: [energia@energy.ca.gov]



 
Dated: December 13, 2002 ENERGY RESOURCES CONSERVATION AND
DEVELOPMENT COMMISSION




ROBERT PERNELL
Commissioner and Presiding Member
SMUD AFC Committee
 
ARTHUR H. ROSENFELD
Commissioner and Associate Member
SMUD AFC Committee




| Project Main Page | Siting Cases Main Page | Commission Homepage | Site Index | Search Site | Links | Contact Us |