The California
Energy Commission SMUD Cosumnes Committee (Committee)
is reviewing an Application for Certification (AFC)
by SMUD to construct two 500 megawatt natural gas-fired
combined cycle power plants near the Rancho Seco
Nuclear Power Plant.
The Committee
conducted the second Evidentiary Hearing on May
13, 2003. Transcripts from this hearing should be
available in approximately two weeks. Earlier Evidentiary
Hearings were held on March 12 and 13, 2003. Transcripts
from these earlier hearing are currently available
on the Energy Commission's web site at:
[www.energy.ca.gov/sitingcases/smud]
In accordance
with discussions among the parties at the conclusion
of the last Evidentiary Hearing, the Committee directs
the parties to prepare and file briefs as follows:
- First Evidentiary Hearing Opening Brief (SMUD
& Staff): May 28, 2003
- First Evidentiary Hearing Opening Brief (Intervenors):
June 4, 2003
- Second Evidentiary Hearing Opening Brief/Reply
Brief (SMUD & Staff): June 13, 2003*
- Second Evidentiary Hearing Opening Brief/Reply
Brief (Intervenors): June 20, 2003*
- Second Evidentiary Hearing Reply Brief (SMUD
& Staff): June 20, 2003*
- Second Evidentiary Hearing Reply Brief (Intervenors):
June 27, 2003*
(* Assumes transcript available by May 30, 2003;
otherwise, schedule slipped day-for-day.)
The Committee
further directs Staff to prepare a Word file of
all the proposed Conditions of Certification and
electronically forward it to the Hearing Officer
by May 30, 2003.
|