[California Energy Commission Letterhead]

STATE OF CALIFORNIA

Energy Resources Conservation
and Development Commission


In the Matter of:                       )     Docket No.: 98-AFC-4
Application for Certification of the    )	
Sunrise Cogeneration and Power Project  )     COMMITTEE REQUEST FOR  	
                                        )     RESPONSE TO APPLICANT'S
                                        )     PROPOSED SCHEDULE
________________________________________)



On September 12, 2000, Sunrise Power Company (Sunrise) submitted an Amended Application for a simple cycle peaking facility. Sunrise followed on September 18, 2000, with a Proposed Schedule (ATTACHMENT A BELOW) as a recommendation for processing the amended Application. Parities are invited to comment on the Sunrise Proposed Schedule in writing no later than September 29, 2000. Any comments should be sent to the Commission Docket Unit, MS-4, 1516 Ninth Street, Sacramento, CA 95814 and served on all parties.

Date On Line: September 19, 2000



ENERGY RESOURCES CONSERVATION
AND DEVELOPMENT COMMISSION



_______//Signature//_______
Gary Fay
Hearing Officer


ATTACHMENT A

SUNRISE PROPOSED SCHEDULE

Amended Application Submitted to CEC September 12, 2000
DOC Application Submitted to SJVUAPCD September 12, 2000
CEC Staff Completes Review of Amended
Application
September 20, 2000
CEC Staff Issues Data Requests September 27, 2000
SJVUAPCD Releases PDOC September 27, 2000
Applicant Responds to Data Requests October 6, 2000
FSA Issued October 24, 2000
Parties File Testimony October 30, 2000
SJVUAPCD Issues FDOC November 6, 2000
Evidentiary Hearings November 8, 2000
(14 days from FSA - §1747)
Revised PMPD Issued November 17, 2000
Special Commission MeetingNoticed November 20, 2000
Special Commission Meeting December 4, 2000
(15 days from Rev. PMPD - §1753)