STATE OF CALIFORNIA
Energy Resources Conservation
and Development Commission In the Matter of: ) Docket No.: 98-AFC-4 Application for Certification of the ) Sunrise Cogeneration and Power Project ) COMMITTEE REQUEST FOR ) RESPONSE TO APPLICANT'S ) PROPOSED SCHEDULE ________________________________________)On September 12, 2000, Sunrise Power Company (Sunrise) submitted an Amended Application for a simple cycle peaking facility. Sunrise followed on September 18, 2000, with a Proposed Schedule (ATTACHMENT A BELOW) as a recommendation for processing the amended Application. Parities are invited to comment on the Sunrise Proposed Schedule in writing no later than September 29, 2000. Any comments should be sent to the Commission Docket Unit, MS-4, 1516 Ninth Street, Sacramento, CA 95814 and served on all parties.
Date On Line: September 19, 2000
ENERGY RESOURCES CONSERVATION
AND DEVELOPMENT COMMISSION
_______//Signature//_______
Gary Fay
Hearing Officer
ATTACHMENT A
SUNRISE PROPOSED SCHEDULE
Amended Application Submitted to CEC September 12, 2000 DOC Application Submitted to SJVUAPCD September 12, 2000 CEC Staff Completes Review of Amended
ApplicationSeptember 20, 2000 CEC Staff Issues Data Requests September 27, 2000 SJVUAPCD Releases PDOC September 27, 2000 Applicant Responds to Data Requests October 6, 2000 FSA Issued October 24, 2000 Parties File Testimony October 30, 2000 SJVUAPCD Issues FDOC November 6, 2000 Evidentiary Hearings November 8, 2000
(14 days from FSA - §1747)Revised PMPD Issued November 17, 2000 Special Commission MeetingNoticed November 20, 2000 Special Commission Meeting December 4, 2000
(15 days from Rev. PMPD - §1753)