GWF Energy LLC (GWF) is seeking approval of an Application
for Certification from the California Energy
Commission for the construction and operation of the Tracy
Peaker Project. GWF proposes to build and operate the
project, a nominal 169- megawatt (MW), simple-cycle power plant,
on a 10.3-acre fenced site within a 40-acre parcel in an
unincorporated portion of San Joaquin County.
The property is bounded by the Delta-Mendota Canal to the
southwest, agricultural property to the south and east, and
the Union Pacific Railroad to the north. Immediately north
of the railroad are the Owens-Brockway glass container
manufacturing plant and the Nutting-Rice warehouse. The
Tracy Biomass power plant is approximately 0.6 miles to the
northwest.
The project would consist of the power plant, an onsite
230-kilovolt (kV) switchyard, an onsite natural gas supply
interconnection, an approximately 1,470-foot water supply
pipeline (as measured from the fence line), and improvements
to an existing dirt access road approximately one mile in
length.