Tracy Peaker Power Plant Project - Main Page
[ California picture montage ]

PROJECT INFO

Project Location (Maps)

COMPLIANCE PROCEEDING
(Updated: 12/19/03)
Notices and Documents

Docket Logs
01-AFC-16C
ORIGINAL PROCEEDING

Notices, Orders,
Hearings & Workshops

(Updated: 07/18/02)

Documents,
Decisions and
Transcripts

(Updated: 08/23/02)

Docket Logs
01-AFC-16
Schedule
For This Case


Proof of
Service List


List of
Reviewing Agencies

Commission
News Releases


PARTICIPATION

Public Adviser's Office

Guide to
Public Participation
In Siting Cases


Overview of
Siting Process


Title 20
Calif. Code of Regulations


Commission
Siting Division


Acronyms
Used in Siting Cases



  TRACY PEAKER
POWER PLANT PROJECT

Docket Numbers: 01-AFC-16 (Application For Certification)
01-AFC-16C
(Compliance Proceeding)


Committee Overseeing the Original Proceeding:

Robert Pernell, Commissioner
Presiding Member

  Robert A. Laurie, Commissioner
Associate Member

Hearing Officer: Cheryl Tompkin
ANNOUNCEMENTS

To Be Announced

Also see our
Energy Calendar


Key Dates
  • 7/17/02 - Project is approved by Energy Commission.

  • 5/31/02 - Presiding Member's Proposed Decision released.

  • 12/28/01 - Staff Assessment of Tracy Peaker Project released.

  • 10/17/01 - AFC determined to be "data adequate."

  • 8/16/2001 - Applicant files Application For Certification (AFC).



General Description of Project

GWF Energy LLC (GWF) is seeking approval of an Application for Certification from the California Energy Commission for the construction and operation of the Tracy Peaker Project. GWF proposes to build and operate the project, a nominal 169- megawatt (MW), simple-cycle power plant, on a 10.3-acre fenced site within a 40-acre parcel in an unincorporated portion of San Joaquin County.

The property is bounded by the Delta-Mendota Canal to the southwest, agricultural property to the south and east, and the Union Pacific Railroad to the north. Immediately north of the railroad are the Owens-Brockway glass container manufacturing plant and the Nutting-Rice warehouse. The Tracy Biomass power plant is approximately 0.6 miles to the northwest.

The project would consist of the power plant, an onsite 230-kilovolt (kV) switchyard, an onsite natural gas supply interconnection, an approximately 1,470-foot water supply pipeline (as measured from the fence line), and improvements to an existing dirt access road approximately one mile in length.


Energy Commission Facility Certification Process

The Energy Commission is the lead agency under the California Environmental Quality Act (CEQA) and has a certified regulatory program under CEQA. Under its certified program, the Energy Commission is exempt from having to prepare an environmental impact report. Its certified program, however, does require environmental analysis of the project, including an analysis of alternatives and mitigation measures to minimize any significant adverse effect the project may have on the environment.


For Questions About This Siting Case Contact:

Lance Shaw
Compliance Project Manager
Systems Assessment and Facility Siting Division
1516 9th Street, MS-2000
Sacramento, CA 95814
Phone 916-653-1227
E-mail: lshaw@energy.state.ca.uss

Internet E-Mail List Server will be available at:
tracypeaker @ energy.ca.gov
(See List Server Page for subscription info.)



For Questions About Participation In Siting Cases Contact:

Public Adviser
California Energy Commission
1516 Ninth Street, MS-12 Sacramento, CA 95814
Phone: 916-654-4489
Toll-Free in California: 1-800-822-6228
E-mail: PAO@energy.state.ca.us



News Media Please Contact:

Claudia Chandler
Assistant Executive Director
Media & Public Communications Office
Phone: 916-654-4989
E-mail: mediaoffice@energy.state.ca.us