Revised Committee Schedule
[California Energy Commission Letterhead]


STATE OF CALIFORNIA

Energy Resources
Conservation and Development Commission



In the Matter of:                   )      Docket No. 01-AFC-16
                                    )
Application for Certification       )      APPLICATION COMPLETE
of the GWF TRACY PEAKER PROJECT     )
IN SAN JOAQUIN COUNTY               )      (DATA ADEQUATE)
                                    )
(GWF ENERGY LLC)                    )      OCTOBER 17, 2001
____________________________________)

 

NOTICE OF REVISED SCHEDULE

 

This NOTICE provides information regarding revised scheduling. The new schedule is attached to the end of this Notice.

Status Update

On March 6, 7, 8, 13, 14 and 28, 2002, the Committee conducted formal evidentiary hearings on GWF Energy LLC's Application for Certification of the Tracy Peaker Project. Upon conclusion of the hearings the parties were granted the opportunity to file post-hearing briefs, and the Committee specifically requested that the parties brief the following legal issues:

  1. In order to find LORS compliance and that the TPP was a permitted use, did the CEC, as the lead agency, have to make all of the findings (and subfindings) the County of San Joaquin would have made had it been the lead agency on the project?

  2. What is the relevance of the City of Tracy's LORS to the CEC siting process?

Post-hearing briefs must be filed no later than 4:00 p.m. on April 11, 2002. An individual party's brief cannot exceed 15 pages. Jointly filed briefs cannot exceed 10 pages per party (e.g., a joint brief by two intervenors may not exceed 20 pages, a joint brief by three intervenors may not exceed 30 pages, etc.)

It is the Committee's intention to issue the Presiding Member's Proposed Decision (PMPD) by the end of May 2002. Issuance of the PMPD will be followed by a 30 day public comment period, and ultimately a decision on the PMPD by the full Commission.

Additional Information

For information on public participation, contact Roberta Mendonca, the Public Adviser, at (916) 654-4489 or (800) 822-6228 or e-mail at: [pao@energy.state.ca.us]

Technical questions concerning the project should be addressed to Cheri Davis, the Commission's Project Manager, at (916) 657-4394 or e-mail at: [cdavis@energy.state.ca.us]

Questions of a legal or procedural nature should be directed to Cheryl Tompkin, the Hearing Officer, at (916) 654-3893 or e-mail at: [ctompkin@energy.state.ca.us]

If you require special accommodations to participate in this proceeding please contact Betty LaFranchi at (916) 654-5204, at least five days prior to the hearing.

Media inquiries should be directed to Claudia Chandler, Assistant Executive Director for Media and Public Communications at (916) 654-4989 or e-mail at: [energia@energy.ca.gov]

Information concerning the status of the project, as well as notices and other relevant documents, is also available on the Energy Commission's Internet home page at: [http://www.energy.ca.gov/sitingcases/tracypeaker]

ENERGY RESOURCES CONSERVATION
AND DEVELOPMENT COMMISSION

Date Online April 5, 2002


Robert Pernell, Commissioner
Presiding Member
GWF Tracy Peaker Project Committee


Robert A. Laurie, Commissioner
Associate Member
GWF Tracy Peaker Project Committee


REVISED COMMITTEE SCHEDULE FOR GWF TRACY PEAKER PROJECT

DAY

DATE

ACTIVITY

 

March 6, 7, 8, 13, 14 & 28,

2002

Evidentiary Hearings

 

April 11, 2002

Parties file post-hearing briefs

 

Late May

Presiding Member's Proposed Decision (PMPD) Issued; Begin 30-day Public Comment Period

 

30 days from issuance of PMPD

End of Public Comment Period on PMPD

 

Late June to early July

Decision on PMPD at Regularly Schedule Business Meeting