DAY |
DATE |
ACTIVITY |
|
0 |
Oct. 17 |
Energy Commission (CEC) determines Application is complete |
| |
Oct 23 |
Staff Files and Serves Data Requests |
|
16
|
Nov. 2 |
Notice of Informational Hearing, Site Visit & Schedule |
| |
Nov. 2 |
Staff Publishes Issue Identification Report |
|
23
|
Nov. 9 |
Committee Determines Application Qualifies: Pub. Resources Code § 25552 |
| |
Nov. 13 |
Applicant Files Data Responses (per Staff) |
| |
Nov. 20 |
Data Request Workshop(s)(per Staff) |
|
42
|
Nov. 28 |
Informational Hearing & Site Visit |
|
50 |
Dec. 7 |
Initial Critical Path Items Required from Applicant -
- Preliminary Determination of Compliance (PDOC)
- Biological Opinion or Equivalent Demonstration of LORS Compliance
- Cal-ISO Transmission Interconnection Review and Approval
- "Will Serve" Letter or Equivalent from Water Supplier
- Demonstration of NPDES Permit Compliance, if Necessary
- Responses to All Data Requests Not Previously Submitted
- Any Other Critical Path Item Known to Applicant
|
|
74 |
Dec. 31 |
Staff files and serves Staff Assessment (including results of Cumulative Impact Study) |
| |
Early Jan. |
Staff Workshop on Staff Assessment |
| |
Early Jan. |
Committee Workshop(s)/Prehearing Conference |
| |
Early Jan. |
Committee Files and Serves Hearing Order |
| |
Early Jan. |
Testimony Filed and Served (Including Amended Staff Assessment) |
| |
Mid Jan. |
Evidentiary Hearing (Possibly Preceded by Committee Workshops) |
| |
End of Jan. |
Presiding Member's Proposed Decision (PMPD) Issued; Begin 30-day Public Comment Period |
|
116 |
Feb. 11 |
Initial Critical Path Items Required from Applicant -
- Corrected Final Determination of Compliance (CFDOC)
- Adopted Final General Plan Amendment, Zoning Ordinance, and/or Conditions Required by Local Agencies but for CEC Jurisdiction
|
| |
30 days from issuance of PMPD |
End of Public Comment Period on PMPD |
|
139 |
Mar. 6 |
Decision on PMPD at Regularly Schedule Business Meeting (if parties are on schedule) |