Valero Cogeneration Power Plant Project - Main Page
[ California picture montage ]

PROJECT INFO

Project Fact Sheet

Project Location (Maps)

COMPLIANCE
PROCEEDINGS

Announcements, Documents,
Notices & Other Info
Relating to the
Compliance Proceeding

(Updated: 11/14/05)

Docket Logs
01-AFC-5C


ORIGINAL PROCEEDING

Notices, Orders,
Hearings & Workshops

(Updated: 10/18/01)

Documents,
Decisions and
Transcripts

(Updated: 11/7/01)

Docket Logs
01-AFC-05

Schedule
For This Case


Electronic Proof of
Service List


Proof of
Service List


Commission
News Releases


PARTICIPATION

Public Adviser's Office

Guide to
Public Participation
In Siting Cases


Overview of
Siting Process


Title 20
Calif. Code of Regulations


Commission
Siting Division


Acronyms
Used in Siting Cases



  VALERO COGENERATION
Power Plant Project

Docket Number: 01-AFC-5C (Compliance Proceeding)
  01-AFC-5    (Application For Certification)


Committee Overseeing This Case:

Arthur H. Rosenfeld, Commissioner
Presiding Member

  Robert A. Laurie, Commissioner
Associate Member

Hearing Officer: Garret Shean
ANNOUNCEMENTS

To Be
Announced

Also see our
Energy Calendar

 

Key Dates

General Description of Project

On May 7, 2001, Valero Cogeneration Project (VCP), wholly owned by Valero Refining Company, Benicia CA., filed an Application for Certification (01-AFC-5) seeking approval from the California Energy Commission (Energy Commission) a 4-month, expedited review to construct and operate the Valero Cogeneration Project.

The site is located at the existing refinery location in Block 25, Township 3 North, Range 3 West of the Benicia Quadrangle, Solano County, Assessor Lot Number for the site is 90-110-03.

VCP will be a nominal 102 megawatts (MW) cogeneration power plant. The proposed facility will include two combustion turbine generators equipped with water injection to control oxides of nitrogen (NOx) emissions and associated support equipment. Phase 1 of the project, a 51 MW generator, went on line commercially on October 18, 2002. Construction of Phase 2 of the project, the final 51 MW generator, is on hold with 37 percent of the project completed (as of September 2003).

The project will be visually compatible with the existing refining equipment in the adjacent areas. The power plant area will be accessed via the existing roads and streets within the refinery. The power plant will consist of a two GE gas turbines (LM6000 - PC Sprint) with chillers, fuel gas compression facilities, power generators, heat recovery steam generators (HRSG), SCRs for emission control, and associated instrumentation, piping, and wiring. The produced power will be conveyed about 2,000 feet through underground cables to the new Valero switch house within the refinery at a voltage of 12 kilovolt. As a result of this project, the refinery will not need power currently provided from the California electrical grid.


Energy Commission Facility Certification Process

The Energy Commission is the lead agency under the California Environmental Quality Act (CEQA) and has a certified regulatory program under CEQA. Under its certified program, the Energy Commission is exempt from having to prepare an environmental impact report. Its certified program, however, does require environmental analysis of the project, including an analysis of alternatives and mitigation measures to minimize any significant adverse effect the project may have on the environment.


For Questions About This Siting Case Contact:
Chris Davis
Compliance Project Manager
Systems Assessment & Facility Siting Division
California Energy Commission
1516 Ninth Street MS 2000
Sacramento, CA 95814
Phone: 916-654 4842
E-mail: CMDavis@energy.state.ca.us


For Questions About Participation In Siting Cases Contact:
Public Adviser's Office
California Energy Commission
1516 Ninth Street, MS-12 Sacramento, CA 95814
Phone: 916-654-4489
Toll-Free in California: 1-800-822-6228
E-mail: PAO@energy.state.ca.us



News Media Please Contact:

Claudia Chandler
Assistant Executive Director
Media & Public Communications Office
Phone: 916-654-4989
E-mail: mediaoffice@energy.state.ca.us




| Homepage | Commission Info | Licensing Main Page | Calendar | Site Index | Search Site | Links | Contact Us |

Page Updated: November 17, 2003