CALIFORNIA |
NOTICE OF PUBLIC INFORMATIONAL HEARING & SITE VISIT |
|
|
1516 Ninth Street |
|
VALERO COGENERATION PROJECT |
|
|
The California Energy Commission is the State agency granted exclusive authority to review and license proposals to construct and operate large electric power plants. Valero Refining Company-California has filed a proposal to construct a cogeneration power plant project at the existing Valero Benicia Refinery near the City of Benicia in Solano County. A Committee of the Commission will begin the regulatory review process by conducting a Public Informational Hearing and Site Visit as described below: |
|
|
|
|
|
Purpose of Hearing: |
The Informational Hearing and Site Visit are
the initial steps of the Commissions public power plant certification
process, which contains requirements equivalent to those under the California
Environmental Quality Act (CEQA) to review all relevant environmental
and engineering aspects of the proposed project.
At the Informational Hearing, members of the general public, landowners,
and representatives of other governmental agencies will have an opportunity
to obtain information and offer comments on the proposal. The Applicant,
Valero Refining Company, will explain its plans for developing the proposed
site and related facilities. The Energy Commission staff will explain
the regulatory review process and staffs role as independent experts
in analyzing the project. The Applicant and the staff will also discuss
possible issues that may be significant during the remainder of the proceeding. |
|
|
|
|
Hearing Date & Place: |
Thursday, July 12, 2001 |
|
|
|
|
Site Visit: Reservations Required: |
The Informational Hearing will be preceded by a Site Visit during daylight
hours, at 5:00 p.m. at the Valero Benicia Refinery. Persons intending
to attend the Site Visit should gather at the Valero Benicia Refinery
(3400 E. Second St, Benicia) parking lot. The Applicant will provide bus
transportation and guides within its Refinery property. |
|
|
|
|
Project Description: |
On May 7, 2001, Valero Cogeneration Project (VCP), wholly owned by Valero
Refining Company, Benicia CA., filed an Application for Certification
(01-AFC-5) seeking approval from the California Energy Commission (Energy
Commission) a 4-month, expedited review to construct and operate the Valero
Cogeneration Project. The site is located at the existing Valero Benicia
refinery. |
|
|
|
|
More Information: |
In order to assist participants in understanding the project, the Commission
Staff will prepare and file by June 22, 2001 an Issue Identification Report
summarizing the potential major issues in the proceeding. Copies of this
document may be obtained by calling the Commissions Project Manager
at (916) 653-0062 or through the Commissions Web Site. |
|
|
|
|
Help: |
Members of the public may participate in all phases of the licensing
process in a variety of ways. If you need information concerning public
participation, please contact Roberta Mendonca, the Energy Commissions
Public Adviser, at 916-654-4489 or, toll free in California, at 800-822-6228,
or by e-mail at: pao@energy.state.ca.us |
|
|
|
|
Contacts: |
Technical questions concerning the project should be addressed to the
Energy Commission Staffs Project Manager, Jack Caswell, at 916-653-0062
or e-mail at: jcaswell@energy.state.ca.us |
|
Dated: June 19, 2001 |
ENERGY RESOURCES CONSERVATION AND DEVELOPMENT COMMISSION |
|
|
|
|
|
|
|
_______/s/______________________ |
_______/s/______________________ |
|
|
|