Power Plant Projects Withdrawn By Applicants Or Terminated By Commission

Please note: Background files and documents for withdrawn projects were removed from the website about one to two months after the project had withdrawn. Withdrawn projects do not include projects that are postponed, suspended or on hold. "Withdrawn" projects have formally asked that their application or license be ended. Copies of AFCs for these projects may be available through the Commission's project managers. However, some of the older applications did not require electronic AFCs. Please contact our siting office at 916-654-4074 for assistance.

Projects Withdrawn in 2008
Project Applicant / Host Size
(megawatts)
Location AFC Filing Date   [1] Commission Action   [2] Withdrawl Date  [3]
Bullard Energy Center
(06-AFC-8)
Bullard Energy
Center LLC
200 MW Fresno County AFC Filed
November 6, 2006
Data Adequate
January 3, 2007
AFC withdrawn by applicant
2/22/08
Total Withdrawn in 2008
200 MW
 


Projects Withdrawn in 2007
Project Applicant / Host Size (megawatts) Location AFC Filing Date  [1] Commission Action  [2] Withdrawl Date  [3]
South Bay Replacement Project
(06-AFC-3)
LS Power South Bay LLC 620 MW San Diego County AFC Filed
June 30, 2006
Never Declared "Data Adequate" LS Power withdraws AFC
10/22/07
Total Withdrawn in 2007
620 MW
 


Projects Withdrawn in 2006
Project Applicant / Host Size (megawatts) Location AFC Filing Date  [1] Commission Action  [2] Withdrawl Date  [3]
Avenal
(01-AFC-20)
Avenal 600 MW Kings County AFC Filed
October 9, 2001
Data Adequate
December 19, 2001
Commission terminates proceeding
12/13/06
City of Vernon Combined Cycle
(06-AFC-1)
City of Vernon 610 MW Los Angeles County AFC Filed
March 2, 2006
Never Declared "Data Adequate" Application Withdrawn
4/6/06

(Project replaced
by 06-AFC-3)
Potrero Unit 7
(00-AFC-4)
Mirant 540 MW San Francisco County AFC Filed
May 31, 2000
Data Adequate
October 20, 2000
Commission terminates proceeding
3/1/06
Total Withdrawn in 2006
1,750 MW
 



None Withdrawn in 2005



Projects Withdrawn in 2004
Project Applicant / Host Size (megawatts) Location AFC Filing Date  [1] Commission Action  [2] Withdrawl Date  [3]
Los Banos
(01-AFC-23)
Cummins West 80 MW Merced County AFC Filed
November 26, 2001
Never Declared "Data Adequate" WITHDRAWN
4/29/04
Total Withdrawn in 2004
80 MW
 



None Withdrawn in 2003


Projects Withdrawn in 2002
Project Applicant / Host Size (megawatts) Location AFC Filing Date  [1] Commission Action  [2] Withdrawl Date  [3]
Colusa Power Project
(01-AFC-10)
Reliant Energy 500 MW Colusa County AFC Filed
July 6, 2001
Data Adequate
August 15, 2001
WITHDRAWN
5/14/02
Gilroy Energy Center Phase II
(01-AFC-9)
Calpine 135 MW Santa Clara County AFC Filed
June 15, 2001
Never declared "Data Adequate" WITHDRAWN
10/4/02
Pegasus Power Project, Chino
01-EP-9
Pegasus Power Partners, LLC 180 MW California Correctional Institution for Men, Chino AFC Filed
May 11, 2001
AFC APPROVED
by Commission
6/8/01
WITHDRAWN
1/3/02
Pastoria Expansion
(01-AFC-2)
Enron 250 MW Tejon Ranch,
Kern County
AFC Filed
February 16, 2001
Never declared "Data Adequate" WITHDRAWN
10/15/02
Rio Linda / Elverta
(01-AFC-1)
Florida Power & Light 560 MW Sacramento County AFC Filed
February 2, 2001
Data Adequate
April 18, 2001
WITHDRAWN
8/20/02
Roseville Energy Facility
(01-AFC-14)
Roseville Energy Facility LLC (Enron) 900 MW Roseville
Placer County
AFC Filed
August 10, 2001
Data Adequate
October 17, 2001
WITHDRAWN
11/19/02
Spartan I Energy Center
(01-AFC-13)
Spartan Power LLC 96 MW San Jose
Santa Clara County
AFC Filed
August 9, 2001
Never declared "Data Adequate" WITHDRAWN
11/21/02
South Star Cogeneration Project
(01-AFC-15)
South Star Cogeneration LLC 200 MW Near Taft
Kern County
AFC Filed
August 13, 2001
Never declared "Data Adequate" WITHDRAWN
11/27/02
Total Withdrawn in 2002
2,821.0 MW
 


Projects Withdrawn in 2001
Project Applicant / Host Size (megawatts) Location AFC Filing Date  [1] Commission Action  [2] Withdrawl Date  [3]
Cenco Electric Peaker Project
(01-EP-15)
CENCO Electric company 50 MW Los Angeles County AFC Filed
6/25/2001
WITHDRAWN
7/27/01
Hanford
(00-SPPE-1)
GWF Power Systems Company 99 MW Hanford,
Kings County
Small Power Plant Exemption (SPPE) Filed
May 19, 2000
AFC APPROVED
by Commission
4/11/01
WITHDRAWN
4/26/01
La Jolla Baldwin Peaking Project
(01-EP-11)
La Jolla Energy Development, Inc. 53 MW Baldwin Hills
Los Angeles County
AFC Filed
5/18/2001
WITHDRAWN
6/21/01
Lancaster Energy Facility #1
(01-EP-12)
Electricity Provider, Inc. 240 MW Lancaster
Los Angeles County
AFC Filed
5/24/2001
WITHDRAWN
7/24/01
Malburg Generating Station Project
(01-AFC-11)
City of Vernon 80.6 MW Vernon,
Los Angeles County
AFC Filed
August 2, 2001
WITHDRAWN
8/23/01
Nueva Azalea
(Formerly known as Sunlaw)
(00-AFC-3)
Sunlaw Cogen. Partners 550 MW South Gate,
Los Angeles County
AFC Filed
March 8, 2000
WITHDRAWN
11/5/01
Ocotillo Energy Project, Phase I (OEP-I)
(01-AFC-8)
Ocotillo Energy LP (Ocotillo) 456 MW City of Palm Springs AFC Filed
May 29, 2001
WITHDRAWN
9/18/01
RAMCO Chula Vista
(01-EP-3)
RAMCO 62.4 MW Chula Vista,
San Diego County
AFC Filed
April 5, 2001
AFC APPROVED
by Commission
6/13/01
WITHDRAWN
7/11/01
Total Withdrawn in 2001
1,591.0 MW
 


Projects Withdrawn in 2000
Project Applicant / Host Size (megawatts) Location AFC Filing Date  [1] Commission Action  [2] Withdrawl Date  [3]
Eastshore Substation Reliability Generation Project
(00-AFC-10)
Calpine c* Power 91.2 MW Alameda County AFC Filed
10/10/2000
WITHDRAWN
10/18/00
Martin Substation Peaking Project
(00-AFC-8)
Calpine c* Power 91.2 MW Brisbane
San Mateo County
AFC Filed
10/10/2000
WITHDRAWN
11/6/00
Newark Substation Reliability Generation Project
(00-AFC-9)
Calpine c* Power 91.2 MW Alameda County AFC Filed
10/10/2000
WITHDRAWN
11/6/00
San Francisco Bay Barge-Mounted Emergency Generator
(00-SPPE-2)
PG&E National Energy Group 95 San Francisco Small Power Plant Exemption (SPPE) Filed
July 12, 2000
WITHDRAWN
8/4/00
San Mateo Substation Peaking Project
(00-AFC-7)
Calpine c* Power 91.2 MW San Mateo County AFC Filed
10/10/2000
WITHDRAWN
11/6/00
Scott Substation Peaking Project
(00-AFC-6)
Calpine c* Power 88 MW Santa Clara County AFC Filed
10/10/2000
Data Adequate
October 31, 2000
WITHDRAWN
11/13/00
Warnerville Substation Reliability Generation Project
(00-AFC-11)
Calpine c* Power 86.2 MW Oakdale
Stanislaus County
AFC Filed
10/10/2000
Data Adequate
October 31, 2000
WITHDRAWN
12/6/00
Total Withdrawn in 2000
634.0 MW
 
 
TOTAL WITHDRAWN
2000-2008
7,696.0 MW