MECP1 Santa Clara 1, LLC (Applicant) is seeking an exemption from the Energy Commission’s jurisdiction (Small Power Plant Exemption, or SPPE) and proceed with local approval rather than requiring an Energy Commission license. In reviewing an SPPE application the Energy Commission acts as the lead agency under section 25519(c) of the Public Resources Code and, in accordance with CEQA, will perform any required environmental analysis.
The applicant proposes to construct and operate the Laurelwood Data Center (LDC or project) in Santa Clara, California. The LDC would consist of two multi-storied data center buildings, 56 3.0 megawatt (MW) standby backup diesel-fired generators capable of providing electrical power during utility outages or certain onsite electrical equipment interruption or failure. The maximum electrical load of the LDC would be 99 MW, inclusive of tenant-installed information technology (IT) equipment in the LDC and cooling and ancillary electrical and telecommunications equipment operating to support IT equipment. The LDC would also include an onsite 60 kilovolt (kV) substation with an electrical supply line that would connect to a Silicon Valley Power (SVP) distribution line located 0.1 miles west of the LDC. To make way for the project, demolition of asphalt/foundations and underground utilities would be necessary, prior to construction.