The Morton Bay Geothermal Project (MBGP or project) would be a geothermal electric power generating facility (PGF). The project would be fitted with one steam turbine generator (STG) system (manufacturer undetermined) consisting of a condensing turbine generator set with three steam entry pressures. Turbine quality geothermal steam from the geothermal resource production facility (RPF) would be the only fuel used by the PGF. MBGP’s maximum continuous rating would be approximately 157 megawatts (MW) gross output, an expected net output of approximately 140 MW, with a maximum annual electrical production of 1,226,400 MW-hours. MBGP would be designed and constructed in accordance with the design criteria provided in Appendix 2B (Jacobs 2023F) in accordance with applicable laws, ordinances, regulations, and standards (LORS).