Project Owner
R&L Capital, Inc.
Docket Number
26-SPPE-01
Capacity
99 MW
Location
Inyokern, Kern County, California
Technology
Backup Generating System
Project Status
Under Review
Project Type
Small Power Plant Exemption
Project Description

The RB Inyokern Data Center (RBIDC) would include a total of forty (40) diesel-fired generator sets that would be used exclusively to provide up to 99 megawatts (MW) of backup emergency generation to support on-site, data center operations during utility outages. Each generator would have a generating capacity of 3 MW. Of the 40 generators, approximately 70 percent would be dedicated to replacing the critical IT load of the data center, while the remaining capacity would be used to support general facility loads, building systems, and life-safety services during emergency outages. The RBIDC emergency backup generating facility would not be electrically interconnected to the transmission or distribution grid, and would not participate in demand response, peak shaving, or any grid-support operations.  

The proposed project site is located near the intersection of U.S. Highway 395 and State Route 178 in Inyokern, an unincorporated area of Kern County, California. The data center building, emergency backup generating facility, on-site substation, fuel storage, cooling systems, site circulation, and parking would be located on Kern County APNs 084-010-43, 084-010-44, a portion of 084-010-45, and a portion of 084-010-48. The total project site encompasses approximately 50 acres of industrially zoned land. The single-story data center building will be approximately 238,000 square feet, with a maximum structural height of 30 feet. 

The forty generators would be arranged in two secured generator yards of twenty (20) units each, positioned on opposite sides of the main data center building to ensure load distribution and operational redundancy. All generators would be equipped with Tier 4 Final emissions controls, including selective catalytic reduction (SCR), diesel oxidation catalyst, and diesel particulate filters (DPF). The facility would include a new customer-dedicated 115/34.5 kilovolt (kV) substation served by two independent 115 kV feeders from Southern California Edison (SCE) and supported by two 60/80/100 MVA transformers configured for redundancy, connecting to SCE's existing infrastructure via underground gen-tie facilities at SCE's Inyokern Substation. On-site fuel storage would be sized to sustain 72 hours of continuous operation at full design load, consistent with Tier III data center reliability criteria. 

Small Power Plant Exemption

The CEC has the exclusive authority to certify all thermal power plants 50 megawatts (MW) and larger and related facilities proposed for construction in California. The Small Power Plant Exemption (SPPE) process allows applicants with facilities between 50 and 100 MW to obtain an exemption from CEC’s jurisdiction and proceed with local permitting rather than requiring CEC certification. CEC can grant an exemption if it finds that the proposed facility would not create a substantial adverse impact on the environment or energy resources. Public Resources Code section 25519(c) designates CEC as the “lead agency”, in accordance with the California Environmental Quality Act (CEQA), for all facilities seeking an SPPE. In granting an SPPE, the CEC is not the final approval necessary for construction and operation of a project. Instead, if the CEC grants an SPPE, the responsible local land use authorities and other agencies, such as the local air management district, will assume jurisdiction over the project under their respective permitting processes, and conduct any other necessary environmental review as “responsible agencies” under CEQA.

Original Proceeding

e-Commenting is currently closed and will open here when available.

Submit e-Filing

Docket Log (26-SPPE-01)

Exhibit List

Proof of Service List

Search All Power Plant Documents

Contacts

Project Manager

Ali Jahani
STEPsiting@energy.ca.gov
(Please enter project name in the email subject line)
+1 279-226-1175

Public Participation Questions

Public Advisor
publicadvisor@energy.ca.gov
916-269-9595

Media Inquiries

Media & Public Communications Office
mediaoffice@energy.ca.gov
916-654-4989

Subscribe RB Inyokern Data Center