- Project Owner
- Sacramento Municipal Utility District (SMUD)
- Docket Number
- 01-AFC-19C
- Capacity
- 603 MW
- Location
- Sacramento County
- Technology
- Combined Cycle
- Project Status
- Operational (Natural Gas-Fired)
- Project Type
- Application for Certification
The Cosumnes Power Plant (CPP) is located adjacent to the Rancho Seco Nuclear Plant, 25 miles southeast of the city of Sacramento, Sacramento County.
The CPP is a nominal 603-megawatt (MW) combined-cycle, natural gas-fired facility consisting of two combustion turbines, one condensing steam turbine, and two heat recovery steam generators. The transmission line consists of 0.4 miles of new 230-kilovolt line from the on-site switchyard to the existing switchyard at Rancho Seco. The natural gas line is supplied by 26-miles of the district-owned gas line. The line is located between the project site and the Carson Ice-Gen Facility, in Sacramento County. A 0.4-mile connection to the existing 66-inch diameter water line conveys water from the Folsom-South Canal.
The original Application for Certification was for a two-phase project, each phase consisting of 500 MW. Phase 2 was never constructed. In the event the Sacramento Municipal Utility District (SMUD) files an Application for Certification for Phase 2 (500 MW) of the project, the CEC’s review will be limited to Air Quality, Water Resources (including the use of recycled water for cooling based upon the stipulation between SMUD and Commission staff), and Transmission System Engineering unless any of the circumstances identified in the CEQA Guidelines, section 15162 (a)(1)-(3) regarding substantive changes or new information have occurred or there have been changes to applicable law.
- Axial Fuel Staging System TN 264442 Submitted 06/24/2025
- Operation of Facility in Simple-Cycle Mode TN 244135 Submitted 7/20/2022
- Change Project Name to Cosumnes Power Plant TN 238883 Submitted 07/15/2021
- Modification of Condition of Certification AQ-30 TN 233809 Submitted 07/08/2020
- Replacement of ZLD Evaporator and Sump Vessel Not in Docket Submitted 8/28/2019
- Addition of New Candle Filter Press Not in Docket Submitted 02/06/2019
- Operation of Installed Advanced Gas Path Upgrades TN 226231 Submitted 01/07/2019 (Order No. 18-1210-04)
- Upgrade Turbine and Emission Control System Components Not in Docket Submitted 01/08/2018
- Modification to Fuel Supply TN 62843 Submitted 11/08/2011 (Order No. 11-1102-05)
- Move Main Entry Gate 130 feet to the North Not in Docket Submitted 07/19/2010
- Relocation of a one-mile segment of 26-mile natural gas pipeline Not in Docket Submitted 04/28/2009
- Upgrade to ZLD and Installation of OnePass Filtration System TN 51120 Submitted 04/16/2009
- Modification to Air Quality Conditions of Certification TN 46617 Submitted 06/06/08 (Order No. 08-0604-01)
- Ownership Transfer to Sacramento Municipal Utility District Financing Authority TN 35811 Submitted 10/26/2005 (Order No. 05-1019-01a)
- Relocation of Water Supply Line TN 30641 Submitted 01/28/2009
- Installation of Temporary Concrete Batch Plant TN 30799 Submitted 01/29/2004
Attention: Non-hypertext items above will need to be requested from the Compliance Project Manager, along with the document TN number, if provided above.
Power Plant Certification and Exemption Processes
The CEC has the exclusive authority to certify all thermal power plants 50 megawatts (MW) and larger and related facilities proposed for construction in California. The Application for Certification (AFC) process is a certified regulatory program under the California Environmental Quality Act (CEQA). As a certified regulatory program, the CEC does not prepare environmental impact reports (EIRs) in an AFC proceeding, but instead prepares environmental assessment documents that are functionally equivalent to EIRs. A certificate issued by the CEC is in lieu of any permit, certificate, or similar document otherwise required by any state, local or regional agency, or federal agency to the extent permitted by federal law, and supersedes any applicable statute, ordinance, or regulation of any state, local, or regional agency, or federal agency to the extent permitted by federal law.
Original Proceeding
e-Commenting has been closed. Please submit your comments in compliance proceeding above.
Contacts
Project Manager
Ashley Gutierrez
CME@energy.ca.gov
(Please enter project name in the email subject line)
916-839-0400
Public Participation Questions
Public Advisor
publicadvisor@energy.ca.gov
916-269-9595
Media Inquiries
Media & Public Communications Office
mediaoffice@energy.ca.gov
916-654-4989