- Project Owner
- Calpine
- Docket Number
- 01-EP-08
- Capacity
- 135 MW
- Location
- Santa Clara County
- Technology
- Simple Cycle
- Project Status
- Operational (Natural Gas-Fired)
- Project Type
- Emergency Peaker
The Gilroy Energy Center is located adjacent to the Gilroy Cogeneration Project, at 1350 Pacheco Pass Highway, Gilroy, Santa Clara County.
GEC is a 135-megawatt natural-gas fired simple-cycle peaking project consisting of three natural gas-fired, aero-derivative LM6000 PC SPRINT combustion turbine generators and associated facilities used to rapidly respond to peak system electricity demands. Highly flexible, quick-responding peaker plants help integrate intermittent renewable resources into the state’s power grid. GEC utilizes recycled water for cooling, and the electricity it generates is committed to the Pacific Gas and Electric Co. under a power purchase agreement.
GEC was reviewed under Public Resources Code section 25705, which granted the California Energy Commission (CEC) emergency permitting authority, and Executive Order D-26-01, issued February 8, 2001 and Executive Order D-28-01 issued on March 7, 2001. In Executive Order D-26-01 and D-28-01, the Governor ordered the CEC and other relevant state and local agencies to expedite review of proposed thermal power plants for construction and operation on an emergency basis by September 30, 2001. The Governor also declared that these projects were emergency projects under Public Resources Code section 21080(b)(4) and are thereby exempt from the requirements of the California Environmental Quality Act.
On May 28, 2003, the CEC approved a Post-Certification Amendment (PCA) (TN 28982) to allow the installation and operation of a Zero Liquid Discharge Wastewater Treatment System at the site.
On June 11, 2003, the CEC approved a PCA (TN 28994) to transfer the ownership of the project from Calpine Corporation to Gilroy Energy Center, LLC, a wholly owned subsidiary of Calpine Corporation. The name of the project was also changed from Gilroy City LM 6000 Phase I Project to Gilroy Energy Center.
The CEC Final Decision included a provision that would allow for the certification to be extended for the life of the project, provided that the conditions of certification were current and in compliance, the project was permanent in nature, and air emission credits were in place. On April 11, 2012, the CEC approved the extension (TN 64744) of GEC for the life of the facility, until such time that it ceases operations and commences permanent closure activities.
- Notice of Insignificant Project Change for Approval to Modify the Design of the Natural Gas Pipeline Reinforcement, TN 28186, 03/05/2003, Staff approval to modify a short section of the 1.7 mile 16-inch Natural Gas Pipeline Reinforcement to the project.
- Order Approving Extension of Online Date, TN 23064, 11/15/2001, Order No. 01-1031-07, Commission approval of an extension of online date from September 30, 2001, to November 30, 2001.
- Order Approving a Petition to Install and operate a Zero Liquid Discharge Wastewater Treatment System, TN 28982, 06/04/2003, Order No. 03-0528-02, Commission approval for installation and operation of a Zero Liquid Discharge Wastewater Treatment System at the site.
- Order Approving a Petition to Change Ownership and Plant Name, TN 28994, 06/13/2003, Order No. 03-0611-01l, Commission approval of transfer ownership/obligations from Calpine Corporation to Gilroy Energy Center, LLC, a wholly-owned subsidiary of Calpine Corporation. Name change to Gilroy Energy Center (GEC).
- Order Affirming Extension of Operational Licenses, TN 64744, 04/13/2012, Order No. 12-0411-05, Commission approval of authority to operate extension pursuant to the terms and conditions of their certifications for the life of the project.
- Authorization for a Software Modification to Allow an Increased Firing Temperature When Warranted, Not in Docket, 11/30/2020, Staff approval of a software change to allow an increased firing temperature when additional megawatts are needed or requested by the California Independent System Operator.
Attention: Non-hypertext items above will need to be requested from the Compliance Project Manager, along with the document TN number, if provided above.
Power Plant Certification and Exemption Processes
The CEC has the exclusive authority to certify all thermal power plants 50 megawatts (MW) and larger and related facilities proposed for construction in California. The Application for Certification (AFC) process is a certified regulatory program under the California Environmental Quality Act (CEQA). As a certified regulatory program, the CEC does not prepare environmental impact reports (EIRs) in an AFC proceeding, but instead prepares environmental assessment documents that are functionally equivalent to EIRs. A certificate issued by the CEC is in lieu of any permit, certificate, or similar document otherwise required by any state, local or regional agency, or federal agency to the extent permitted by federal law, and supersedes any applicable statute, ordinance, or regulation of any state, local, or regional agency, or federal agency to the extent permitted by federal law.
Original Proceeding
e-Commenting has been closed. Please submit your comments in compliance proceeding above.
Contacts
Project Manager
Ashley Gutierrez
CME@energy.ca.gov
(Please enter project name in the email subject line)
916-839-0400
Public Participation Questions
Public Advisor
publicadvisor@energy.ca.gov
916-269-9595
Media Inquiries
Media & Public Communications Office
mediaoffice@energy.ca.gov
916-654-4989