- Docket Number
- 08-AFC-04
- Capacity
- 96 MW
- Location
- San Diego County
- Technology
- Simple Cycle
- Project Status
- Operational (Natural Gas-Fired)
- Project Type
- Application for Certification
The Orange Grove Energy Center (OGEC) peaker power plant is located near State Route 76 (SR-76) in unincorporated San Diego County approximately three miles east of Interstate 15 near the community of Pala.
OGEC is a nominal 99.6-megawatt natural gas-fired, simple-cycle facility consisting of two identical simple-cycle natural gas fired General Electric LM6000 PC SPRINT spray-intercooled combustion turbine generators (Units 1 and 2), inlet air chiller cooling tower, chilled water system package, 0.3-mile underground transmission line from the project to the Pala Substation, a 10-inch 2.4-mile natural gas pipeline connected to the San Diego Gas and Electric main gas line, a 100,000 gallon demineralized storage tank, and a 414 gallon recycled water storage tank. Project emissions are controlled with a carbon monoxide emission oxidation catalyst as well as an aqueous ammonia Selective Catalytic Reduction system that reduces emissions.
- Order Approving Modifications to Air Quality Conditions of Certification, TN 64589, 04/04/2012, Order No. 12-0314-01m, Commission approval to allow OGEP to comply with San Diego County Air Pollution Control District's (SDAPCD) staff recommended changes to the Authority to Construct conditions, and to provide clarification on averaging periods and monitoring requirements for the continuous emission monitoring system (CEMs).
- Order Approving Modifications to Air Quality Conditions of Certification, TN 212333, 07/18/2016, Order No. 16-0713-03, Commission approval to revise Air Quality conditions of certification to restore worn parts of the emission control system and optimize design of system components using like-kind part replacement.
- Statement of Staff Approval. TN 240057, 10/13/2021, Staff approval to modify Air Quality conditions to allow for short term temporary turbine replacement.
Attention: Non-hypertext items above will need to be requested from the Compliance Project Manager, along with the document TN number, if provided above.
Power Plant Certification and Exemption Processes
The CEC has the exclusive authority to certify all thermal power plants 50 megawatts (MW) and larger and related facilities proposed for construction in California. The Application for Certification (AFC) process is a certified regulatory program under the California Environmental Quality Act (CEQA). As a certified regulatory program, the CEC does not prepare environmental impact reports (EIRs) in an AFC proceeding, but instead prepares environmental assessment documents that are functionally equivalent to EIRs. A certificate issued by the CEC is in lieu of any permit, certificate, or similar document otherwise required by any state, local or regional agency, or federal agency to the extent permitted by federal law, and supersedes any applicable statute, ordinance, or regulation of any state, local, or regional agency, or federal agency to the extent permitted by federal law.
Original Proceeding
e-Commenting has been closed. Please submit your comments in compliance proceeding above.
Contacts
Project Manager
Joseph Douglas
CME@energy.ca.gov
(Please enter project name in the email subject line)
916-956-9527
Public Participation Questions
Public Advisor
publicadvisor@energy.ca.gov
916-269-9595
Media Inquiries
Media & Public Communications Office
mediaoffice@energy.ca.gov
916-654-4989